Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2020, February - 2018, February - 2020, March - 2018, March - 2020, April - 2018, April - 2020, May - 2018, May - 2020, June - 2018, July - 2017, August - 2017, August - 2019, September - 2017, September - 2019, October - 2017, October - 2019, November - 2017, November - 2019, December - 2017, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
01-11-03 - - 15-05-17 - 2434.203 1388.746 45 45 25 19.454 1408.2 1000.457 59% 58%
December - 2017
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, Medical ward - plastering in progress.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
01-11-03 - - 15-05-17 - 2434.203 1388.746 45 45 25 4.593 1393.339 1000.457 59% 57%
September - 2017
Phase-2 completed. Phase-3 in progress.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
01-11-03 - - 15-05-17 - 2434.203 1388.746 45 45 25 0 1388.746 1000.457 59% 57%
August - 2017
Phase-2 completed. Phase-3 in progress.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
01-11-03 - - 15-05-17 - 2434.203 1388.746 45 45 0 0 1388.746 1000.457 59% 57%
July - 2017
Phase-2 completed. Phase-3 in progress. Approved for Rs.2903.130 m in PDWP. AA awaited.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.746 45 45 25 15.897 1404.643 1000.457 59% 58%
November - 2017
Phase-2 completed. Phase-3 in progress.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.746 45 45 25 6.853 1395.599 1000.457 59% 57%
October - 2017
Phase-2 completed. Phase-3 in progress.
No Image
1) Phase-II
2) Phase-III
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.296 45 45 45 35.88 1424.176 1000.907 59% 59%
June - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, medical ward - plastering in progress.
No Image
1) Phase-2
2) Phase-3
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.296 45 47.5 47.5 33.618 1421.914 1000.907 59% 58%
May - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, medical ward - plastering in progress.
No Image
1) Phase-2
2) Phase-3
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.296 45 47.5 47.5 28.418 1416.714 1000.907 59% 58%
April - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, medical ward - plastering in progress.
No Image
1) Phase-2
2) Phase-3
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.296 45 45 35.5 28.418 1416.714 1000.907 59% 58%
March - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, Medical ward - plastering in progress.
No Image
1) Phase-2
2) Phase-3
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.296 45 45 35.5 25.551 1413.847 1000.907 59% 58%
February - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, Medical ward - plastering in progress.
ADP's Images
1) Phase-2
2) Phase-3
601
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1388.746 45 45 25 21.153 1409.899 1000.457 59% 58%
January - 2018
Phase-2 completed. Phase-3 (flats, hostel, finishing, store, residences) - SS level. Admin, Medical ward - plastering in progress.
No Image
1) Phase-II 2) Phase-III
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
December - 2019
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
November - 2019
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
October - 2019
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
September - 2019
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
August - 2019
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
May - 2020
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
April - 2020
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
March - 2020
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
February - 2020
No Image
601
(OG)
151045-Special Initiative Programme for PK-30 District Mardan
Mardan
30-11--1 30-11--1 - 30-11--1 - 682.5 421.334 150 150 0 0 421.334 0 - -
January - 2020
No Image
Pages : 1