Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% December - 2019 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 0.836 | 0.836 | 1.06 | 70% |
23% November - 2019 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 0 | 0 | 1.06 | 70% |
- October - 2019 |
Work strated. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- September - 2019 |
Tender under process. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 0 | 0 | 0 | 0 | 0 | 3.56 | - |
- August - 2019 |
Tender under process. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% May - 2020 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% April - 2020 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% March - 2020 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% February - 2020 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.56 | 0 | 2.5 | 2.5 | 2.5 | 2.5 | 2.5 | 1.06 | 70% |
70% January - 2020 |
50% work completed. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% December - 2019 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- November - 2019 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 0 | 0 | 0 | 0 | 0 | 5.574 | - |
- October - 2019 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% May - 2020 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% April - 2020 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% March - 2020 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% February - 2020 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.574 | 0 | 2 | 2 | 2 | 0.994 | 0.994 | 3.574 | 36% |
18% January - 2020 |
Revised scope of work awaited. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
50% December - 2019 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
50% November - 2019 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
50% October - 2019 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | - |
- September - 2019 |
Work order issued. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | - |
- August - 2019 |
Work order issued. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 4.39 | 4.39 | 4.39 | 4.39 | 4.39 | 0 | 100% |
100% May - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 4.39 | 4.39 | 4.39 | 4.39 | 4.39 | 0 | 100% |
100% April - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 4.39 | 4.39 | 4.39 | 4.39 | 4.39 | 0 | 100% |
100% March - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 4.39 | 4.39 | 4.39 | 4.39 | 4.39 | 0 | 100% |
100% February - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 50% |
50% January - 2020 |
Completed. |
No Image |
Construction of Motorcycle Shed. | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. Not yet approved. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. Not yet approved. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
160479-Construction of Newspaper Market for Hawkers in all Districts. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. |
No Image |
Kohat | |||||||||||||||||||
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0.758 | 0.758 | 0 | 100% |
51% December - 2019 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 0 | 100% |
- May - 2020 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 0 | 100% |
- April - 2020 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 0 | 100% |
- March - 2020 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0 | 0 | 0 | 100% |
- February - 2020 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Kohistan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1.5 | 0 | 1.5 | 1.5 | 1.5 | 0.758 | 0.758 | 0 | 100% |
51% January - 2020 |
Boundary wall work in progress. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- December - 2019 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- November - 2019 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- May - 2020 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- April - 2020 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- March - 2020 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- February - 2020 |
Work Order being issued. |
No Image |
595 (OG) |
180076-Additional facilities and improvement of infrastructure of existing judicial complexes |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 14.222 | 0 | 0 | 0 | 0 | 0 | 0 | 14.222 | - |
- January - 2020 |
Work Order being issued. |
No Image |
595 (OG) |
150137-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Mansehra. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 137.445 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
Site/scope of work not identified. |
No Image |
Mansehra | |||||||||||||||||||
Pages : 1 2 |