Progressive Review for the month(s) of : January - 2020, February - 2020, March - 2020, April - 2020, May - 2020, July - 2018, August - 2019, September - 2018, September - 2019, October - 2019, November - 2019, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 4 4 4 4 5.5 21.699 20% 20%
December - 2019
Foundation in progress. BW in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 4 4 4 4 5.5 21.699 20% 20%
November - 2019
Foundation in progress. BW in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 4 4 4 1 2.5 21.699 20% 9%
October - 2019
Foundation in progress. BW in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 1 1 1 1 2.5 24.699 9% 9%
September - 2019
Foundation in progress. BW in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 0 0 0 0 1.5 25.699 - 6%
August - 2019
Foundation in progress. BW in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 14 14 14 4 5.5 11.699 57% 20%
May - 2020
Foundation comleted. Up to plinth beam in progress. Water supply O/H tank in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 14 14 14 4 5.5 11.699 57% 20%
April - 2020
Foundation comleted. Up to plinth beam in progress. Water supply O/H tank in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 14 14 14 4 5.5 11.699 57% 20%
March - 2020
Foundation comleted. Up to plinth beam in progress. Water supply O/H tank in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 14 14 14 4 5.5 11.699 57% 20%
February - 2020
Foundation comleted. Up to plinth beam in progress. Water supply O/H tank in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 27.199 1.5 4 4 4 4 5.5 21.699 20% 20%
January - 2020
Foundation comleted. Up to plinth beam in progress. Water supply O/H tank in progress.
No Image
Bachelor Hostel for Judicial Officers in District Buner
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 3.238 9.535 18.446 50% 26%
December - 2019
Raft laid, GF column in progress.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 3.238 9.535 18.446 50% 26%
November - 2019
Raft laid, GF column in progress.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 2 8.297 18.446 50% 23%
October - 2019
Raft laid, GF column in progress.
No Image
Dir Lower
592
(OG)
150658-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 137.445 0 2 2 0 0 0 0 - -
September - 2018
Site not yet identified by client deptt.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 2 2 2 2 8.297 28.446 23% 23%
September - 2019
Raft laid, GF column in progress.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 0 0 0 0 6.297 30.446 - 17%
August - 2019
Raft laid, GF column in progress.
No Image
Dir Lower
592
(OG)
150658-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 137.445 0 2 2 0 0 0 0 - -
July - 2018
Site not yet identified by client deptt.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 12 18.297 18.446 50% 50%
May - 2020
GF roof laid.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 12 18.297 18.446 50% 50%
April - 2020
GF roof laid.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 12 18.297 18.446 50% 50%
March - 2020
GF roof laid.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 12 18.297 18.446 50% 50%
February - 2020
GF roof laid.
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 36.743 6.297 12 12 12 7.502 13.799 18.446 50% 38%
January - 2020
Raft laid, GF slab form workn in progress
No Image
Dir Lower
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
December - 2019
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
November - 2019
Technical bid opening on 12/11/2019.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
October - 2019
Technical bid opening on 12/11/2019.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
May - 2020
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
April - 2020
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
March - 2020
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
February - 2020
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 26.647 0 0 0 0 0 0 26.647 - -
January - 2020
Technical bid approval under process.
No Image
Construction of Bachelor Hostel for Judicial Officers in Hangu
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
December - 2019
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
November - 2019
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 0 5.25 21.183 25% 18%
October - 2019
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 0 5.25 21.183 25% 18%
September - 2019
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 0 0 0 0 5.25 23.183 - 18%
August - 2019
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 49.102 49.102 49.102 49.101 54.351 0 100% 100%
May - 2020
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
April - 2020
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
March - 2020
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
February - 2020
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Karak
30-11--1 30-11--1 - 30-11--1 - 28.433 5.25 2 2 2 2 7.25 21.183 25% 25%
January - 2020
Main building - column completed. Roof slab steel fabrication in progress.
No Image
Karak
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
December - 2019
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
November - 2019
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
October - 2019
Contract cancelled and will be re-tender after decision of site. Site changing involved.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
September - 2019
Contract cancelled and will be re-tender after decision of site. Site changing involved.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
August - 2019
Contract cancelled and will be re-tender after decision of site. Site changing involved.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
May - 2020
Financial bids approval under process.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
April - 2020
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
March - 2020
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
February - 2020
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat
592
(OG)
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 27.828 0 0 0 0 0 0 27.828 - -
January - 2020
Contract cancelled and tender re-invited on 26/12/2019.
No Image
Kohat