Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
- | - | - | - | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
- | - | - | - | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
- | - | - | - | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
- | - | - | - | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Scope/site of work not identified. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 10 | 0 | 0 | 0 | 0 | 490 | 2% |
- June - 2018 |
Tender approval under process. |
No Image |
Dir Lower | |||||||||||||||||||
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 10 | 10 | 2.5 | 0 | 0 | 490 | 2% |
- May - 2018 |
Tender approval under process. |
No Image |
Dir Lower | |||||||||||||||||||
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 10 | 10 | 0 | 0 | 0 | 490 | 2% |
- April - 2018 |
Tender floated on 25/04/2018. Technical brouchers submitted to SE. |
No Image |
Dir Lower | |||||||||||||||||||
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 10 | 10 | 0 | 0 | 0 | 490 | 2% |
- March - 2018 |
Tender floated on 25/04/2018. |
No Image |
Dir Lower | |||||||||||||||||||
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 10 | 10 | 0 | 0 | 0 | 490 | 2% |
- February - 2018 |
Approved. |
No Image |
589 (New) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 2912 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Scope/site of work not identified. |
No Image |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 20.874 | 73.415 | 142.459 | 43% |
29% December - 2019 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 20.874 | 73.415 | 142.459 | 43% |
29% November - 2019 |
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 20.121 | 72.662 | 142.459 | 43% |
29% October - 2019 |
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 13.75 | 13.75 | 13.75 | 13.75 | 66.291 | 183.709 | 27% |
27% September - 2019 |
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 0 | 0 | 0 | 0 | 52.541 | 197.459 | - |
21% August - 2019 |
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 44.31 | 44.31 | 44.31 | 42.445 | 94.986 | 153.149 | 39% |
38% May - 2020 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 33.621 | 86.162 | 142.459 | 43% |
34% April - 2020 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 33.621 | 86.162 | 142.459 | 43% |
34% March - 2020 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 33.621 | 86.162 | 142.459 | 43% |
34% February - 2020 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 52.541 | 55 | 55 | 55 | 33.621 | 86.162 | 142.459 | 43% |
34% January - 2020 |
Work ub super structure in progress.
GF - Plaster in progress.
FF - Roof laid.
BW - 50% completed. |
No Image |
Mardan | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
PC-II approved for Rs.10 m on 27/04/2015. Scope of work awaited. Site identified but not yet demarcated. PC-I under preparation. Presentation to HCJ awaited. Proposed site in Mardan. |
No Image |
Peshawar | |||||||||||||||||||
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- December - 2019 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- November - 2019 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- October - 2019 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- September - 2019 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- August - 2019 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- May - 2020 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- April - 2020 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- March - 2020 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- February - 2020 |
No Image | |
589 (OG) |
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts" |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 247 | 52.541 | 55 | 55 | 0 | 0 | 52.541 | 0 | - |
- January - 2020 |
No Image | |