Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% December - 2019 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 37.918 | 778.98 | 67.938 | 92% |
91% November - 2019 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 12.5 | 753.562 | 67.938 | 92% |
88% October - 2019 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 12.5 | 12.5 | 753.562 | 67.938 | 92% |
88% September - 2019 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 0 | 0 | 741.062 | 67.938 | 92% |
86% August - 2019 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% May - 2020 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% April - 2020 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% March - 2020 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% February - 2020 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 859 | 741.062 | 50 | 50 | 50 | 41.894 | 782.956 | 67.938 | 92% |
91% January - 2020 |
Main building, bar room, 90% completed. Balance work - in progress. |
No Image |
Judicial Complex Haripur | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
13-05-16 | 30-06-18 | - | 03-12-14 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 88.051 | 152.029 | 16.001 | 95% |
51% December - 2017 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
13-05-16 | 30-06-18 | - | 03-12-14 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 7.5 | 71.478 | 16.001 | 95% |
24% September - 2017 |
(a) Plinth level. (b) Foundation in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
13-05-16 | 30-06-18 | - | 03-12-14 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 110 | 173.978 | 16.001 | 95% |
58% August - 2017 |
(a) Plinth level. (b) Foundtaion in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
13-05-16 | 30-06-18 | - | 03-12-14 | - | 299.98 | 63.978 | 220.001 | 220.001 | 0 | 0 | 63.978 | 16.001 | 95% |
21% July - 2017 |
(a) Plinth level. (b) Foundtaion in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 56 | 119.978 | 16.001 | 95% |
40% November - 2017 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 25.266 | 89.244 | 16.001 | 95% |
30% October - 2017 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 220.001 | 184.142 | 248.12 | 16.001 | 95% |
83% June - 2018 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Saidu Medical College, Swat | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 220.001 | 184.142 | 248.12 | 16.001 | 95% |
83% May - 2018 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Saidu Medical College, Swat | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 220.001 | 124.33 | 188.308 | 16.001 | 95% |
63% April - 2018 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Saidu Medical College, Swat | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 220.001 | 124.33 | 188.308 | 16.001 | 95% |
63% March - 2018 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Saidu Medical College, Swat | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 165 | 110 | 173.978 | 16.001 | 95% |
58% February - 2018 |
Lecture Theatre - SS in progress.
Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Swat | |||||||||||||||||||
584 (OG) |
130217-Construction of 01 Hostel (60 Rooms), 02 Lecture Theaters and Laboratories at Saidu Medical College, Swat. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 299.98 | 63.978 | 220.001 | 220.001 | 110 | 110 | 173.978 | 16.001 | 95% |
58% January - 2018 |
Lecture Theatre - SS in progress. Laboratories - GF slab laid, FF cloumns in progress. |
No Image |
Pages : 1 |