Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 261.95 | 50 | 50 | 12.5 | 12.5 | 274.45 | 618.984 | 34% |
29% August - 2019 |
Consultant AA Associates.
Main building, high court, judicial lodge - FF in progress.
Liability 70 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% December - 2019 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 44.47 | 94.47 | 830.934 | 11% |
10% November - 2019 |
Consultant AA Associates.
Main building, high court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 45 | 95 | 830.934 | 11% |
10% October - 2019 |
Consultant AA Associates.
Main building, high court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 261.95 | 50 | 50 | 12.5 | 12.5 | 274.45 | 618.984 | 34% |
29% September - 2019 |
Consultant AA Associates.
Main building, high court, judicial lodge - FF in progress. Work Stopped from Last 1 yaer
Liability 50 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% May - 2020 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% April - 2020 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% March - 2020 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% February - 2020 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
120004-Construction of Judicial Complex, Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 930.934 | 50 | 50 | 50 | 50 | 50 | 100 | 830.934 | 11% |
11% January - 2020 |
Consultant AA Associates.
Main building, High court, judicial lodge - FF in progress.
Liability 40 M |
No Image |
Judicial Complex, Chitral. | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
- | - | - | 09-02-16 | - | 1336.811 | 560 | 20 | 20 | 10 | 10 | 570 | 756.811 | 43% |
43% December - 2017 |
Main building - basement roofing in progress, auditorium - RCC wall in progress. Demand Rs.100 m. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
- | - | - | 09-02-16 | - | 1336.811 | 560 | 20 | 20 | 10 | 0 | 560 | 756.811 | 43% |
42% September - 2017 |
Main building - basement roofing in progress, auditorium - RCC wall in progress. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
- | - | - | 09-02-16 | - | 1336.811 | 560 | 20 | 20 | 10 | 0 | 560 | 756.811 | 43% |
42% August - 2017 |
Main building - basement roofing in progress, auditorium - foundation in progress. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
- | - | - | 09-02-16 | - | 1336.811 | 560 | 20 | 20 | 10 | 0 | 560 | 756.811 | 43% |
42% July - 2017 |
Main building - basement roofing in progress, auditorium - foundation in progress. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 20 | 10 | 10 | 570 | 756.811 | 43% |
43% November - 2017 |
Main building - basement roofing in progress, auditorium - RCC wall in progress. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 20 | 10 | 10 | 570 | 756.811 | 43% |
43% October - 2017 |
Main building - basement roofing in progress, auditorium - RCC wall in progress. |
No Image |
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 68.4 | 68.4 | 31.481 | 591.481 | 756.811 | 43% |
44% June - 2018 |
Main building (3 blocks) - Block-1 - 3rd floor roof in progress. Block-2 - top roof in progress. Block-3 - top roof in progress |
No Image |
Nowshera | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 265 | 265 | 29.491 | 589.491 | 756.811 | 43% |
44% May - 2018 |
Main building (3 blocks) - Block-1 - 3rd floor roof in progress. Block-2 - top roof in progress. Block-3 - top roof in progress |
No Image |
Nowshera | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 265 | 265 | 29.491 | 589.491 | 756.811 | 43% |
44% April - 2018 |
Main building (3 blocks) - Block-1 - 3rd floor roof in progress. Block-2 - top roof in progress. Block-3 - top roof in progress |
No Image |
Nowshera | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 265 | 265 | 15 | 575 | 756.811 | 43% |
43% March - 2018 |
Main building (3 blocks) - Block-1 - 3rd floor roof in progress. Block-2 - top roof in progress. Block-3 - top roof in progress |
No Image |
Nowshera | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 270 | 270 | 10 | 570 | 756.811 | 43% |
43% February - 2018 |
Main building (3 blocks ) - Block -I 3rd floor roof in progress.
Block II - Top Roof in progress
Block -III top roof in progress |
No Image |
Nowshera | |||||||||||||||||||
580 (OG) |
150522-Establishment of Nowshera Medical College (Phase-I). |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1336.811 | 560 | 20 | 20 | 10 | 10 | 570 | 756.811 | 43% |
43% January - 2018 |
Main building - basement roofing in progress, auditorium - RCC wall in progress. Demand Rs.100 m. |
No Image |