Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% December - 2019 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% November - 2019 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% October - 2019 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 2 | 2 | 252 | 0 | 100% |
98% September - 2019 |
Finishing in progress.Liability 26 M |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 2 | 2 | 252 | 0 | 100% |
98% August - 2019 |
Finishing in progress.Liability 26 M |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% May - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% April - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% March - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% February - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 258 | 250 | 8 | 8 | 8 | 8 | 258 | 0 | 100% |
100% January - 2020 |
Finishing in progress. |
No Image |
Bannu | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
21-05-07 | 30-06-18 | - | 03-04-14 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% December - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
21-05-07 | 30-06-18 | - | 03-04-14 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 0 | 2249.058 | 63.5 | 98% |
88% September - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
21-05-07 | 30-06-18 | - | 03-04-14 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 0 | 2249.058 | 63.5 | 98% |
88% August - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress.
Rectification work 50% completed.
Revised DCE submitted . Observations attended. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
21-05-07 | 30-06-18 | - | 03-04-14 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 0 | 2249.058 | 63.5 | 98% |
88% July - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Revised PC-I submitted to Health Deptt. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% November - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.375 | 2255.433 | 63.5 | 98% |
88% October - 2017 |
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. |
No Image |
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 24.167 | 24.167 | 21.888 | 2270.946 | 63.5 | 98% |
89% June - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 16.507 | 2265.565 | 63.5 | 98% |
89% May - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% April - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% March - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% February - 2018 |
Pack-1 and 2 - completed.
Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
ADP's Images |
DI.Khan | |||||||||||||||||||
572 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2249.058 | 239.074 | 239.074 | 63 | 6.74 | 2255.798 | 63.5 | 98% |
88% January - 2018 |
Pack-1 and 2 - completed.
Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
Pages : 1 |