Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2020, February - 2018, February - 2020, March - 2018, March - 2020, April - 2018, April - 2020, May - 2018, May - 2020, June - 2018, July - 2017, August - 2019, August - 2017, September - 2019, September - 2017, October - 2019, October - 2017, November - 2019, November - 2017, December - 2019, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
December - 2019
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
November - 2019
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
October - 2019
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 2 2 252 0 100% 98%
September - 2019
Finishing in progress.Liability 26 M
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 2 2 252 0 100% 98%
August - 2019
Finishing in progress.Liability 26 M
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
May - 2020
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
April - 2020
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
March - 2020
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
February - 2020
Finishing in progress.
No Image
Bannu
572
(OG)
130581-Addition, Alteration, Strengthening and Balance Works in Judicial Complex, Bannu (Phase-III).
Bannu
30-11--1 30-11--1 - 30-11--1 - 258 250 8 8 8 8 258 0 100% 100%
January - 2020
Finishing in progress.
No Image
Bannu
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
21-05-07 30-06-18 - 03-04-14 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
December - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
21-05-07 30-06-18 - 03-04-14 - 2551.632 2249.058 239.074 239.074 63 0 2249.058 63.5 98% 88%
September - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
21-05-07 30-06-18 - 03-04-14 - 2551.632 2249.058 239.074 239.074 63 0 2249.058 63.5 98% 88%
August - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work 50% completed. Revised DCE submitted . Observations attended.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
21-05-07 30-06-18 - 03-04-14 - 2551.632 2249.058 239.074 239.074 63 0 2249.058 63.5 98% 88%
July - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Revised PC-I submitted to Health Deptt.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
November - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.375 2255.433 63.5 98% 88%
October - 2017
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended.
No Image
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 24.167 24.167 21.888 2270.946 63.5 98% 89%
June - 2018
Pack-1 & 2 - completed. Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
DI.Khan
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 16.507 2265.565 63.5 98% 89%
May - 2018
Pack-1 & 2 - completed. Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
DI.Khan
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
April - 2018
Pack-1 & 2 - completed. Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
DI.Khan
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
March - 2018
Pack-1 & 2 - completed. Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
DI.Khan
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
February - 2018
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
ADP's Images
DI.Khan
572
(OG)
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2551.632 2249.058 239.074 239.074 63 6.74 2255.798 63.5 98% 88%
January - 2018
Pack-1 and 2 - completed. Pack-3 and 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed.
No Image
Pages : 1