Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2019, January - 2020, February - 2018, February - 2019, February - 2020, March - 2018, March - 2019, March - 2020, April - 2018, April - 2019, April - 2020, May - 2018, May - 2020, June - 2018, July - 2017, August - 2017, August - 2019, September - 2017, September - 2019, October - 2017, October - 2019, November - 2017, November - 2018, November - 2019, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.607 65.085 8.197 90% 83%
December - 2018
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2019
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.607 65.085 8.197 90% 83%
November - 2018
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.607 65.085 8.197 90% 83%
November - 2018
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2019
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2019
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2019
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
August - 2019
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2020
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 22.173 22.173 22.173 8.805 65.283 0 100% 83%
April - 2019
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2020
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.805 65.283 8.197 90% 83%
March - 2019
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.805 65.283 8.197 90% 83%
March - 2019
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2020
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.607 65.085 8.197 90% 83%
February - 2019
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2020
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 78.65 56.478 13.975 13.975 13.975 8.607 65.085 8.197 90% 83%
January - 2019
Original scope completed. Revised scope in progress. RCC wall 90% completed.
No Image
1) Construction of 25 cells
2) Raising and strengtthening of boundary wall
3) Construction of Watch Tower in Picquet
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Bannu
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2020
PC-II approved by TEVTA. LOA issued to consultants. PC-I/DCE submitted. Approved. TEVTA is executing itself.
No Image
Establishment of Govt Technical and Vocational Center for Boys PK-72, Bannu
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
December - 2019
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
November - 2019
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
October - 2019
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
September - 2019
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
August - 2019
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 100 100 100 0 0 31.165 76% -
May - 2020
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
April - 2020
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
March - 2020
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
February - 2020
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 131.165 0 0 0 0 0 0 131.165 - -
January - 2020
Work order issued on 13/10/2017 (GTVC for Boys Umerzai). Site dispute.
No Image
1) GTVC for Boys Umerzai
2) GCT Tangi
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
August - 2019
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
December - 2019
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
November - 2019
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
October - 2019
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
September - 2019
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
May - 2020
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
April - 2020
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
March - 2020
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
February - 2020
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 4.6 0 0 0 0 0 0 4.6 - -
January - 2020
Funds returned to TEVTA for execution by themselves.
No Image
Govt Polytechnic Institure Chitral
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.848 31.731 5 5 5 0 31.731 0 100% 100%
December - 2018
Completed.
No Image
DI.Khan
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2019
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.848 31.731 5 5 5 0 31.731 0 100% 100%
November - 2018
Completed.
No Image
DI.Khan
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.848 31.731 5 5 5 0 31.731 0 100% 100%
November - 2018
Completed.
No Image
DI.Khan
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2019
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2019
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2019
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
August - 2019
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2020
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.848 31.731 0 0 0 0 31.731 0.117 - 100%
April - 2019
Completed.
No Image
DI.Khan
553
(OG)
150752-One Liner Provision for Improvement & Development of Technical Education.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2020
PC-II for Rs.1.800 m approved on 13/06/2016.
No Image
553
(OG)
100456-Construction of High Security Zones in 6 Jails of Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 31.848 31.731 0 0 0 0 31.731 0.117 - 100%
March - 2019
Completed.
No Image
DI.Khan
Pages : 1 2 3