Progressive Review for the month(s) of : January - 2019, January - 2018, February - 2019, February - 2018, March - 2019, March - 2018, April - 2019, April - 2018, May - 2018, June - 2018, July - 2017, July - 2018, August - 2017, September - 2018, September - 2017, October - 2017, November - 2017, November - 2018, December - 2018, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
17-05-13 30-06-18 - 12-04-16 - 750.011 546.382 203.629 203.629 102 43.438 589.82 0 100% 79%
December - 2017
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids being invited.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
17-05-13 30-06-18 - 12-04-16 - 750.011 546.382 203.629 203.629 102 43.5 589.882 0 100% 79%
September - 2017
OPD, main building - finishing in progress. Pre-qualification invited for VRF.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
17-05-13 30-06-18 - 12-04-16 - 750.011 546.382 203.629 203.629 102 0 546.382 0 100% 73%
August - 2017
OPD, main building - finishing in progress.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
17-05-13 30-06-18 - 12-04-16 - 750.011 546.382 203.629 203.629 0 0 546.382 0 100% 73%
July - 2017
OPD, main building - finishing in progress.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 43.438 589.82 0 100% 79%
November - 2017
OPD, main building - finishing in progress. Pre-qualification invited for VRF.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 43.438 589.82 0 100% 79%
October - 2017
OPD, main building - finishing in progress. Pre-qualification invited for VRF.
No Image
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 102 102 69.42 615.802 0 100% 82%
June - 2018
OPD, main building - finishing in progress. VRF syetem - in progress.
No Image
Malakand
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 69.527 615.909 0 100% 82%
May - 2018
OPD, main building - finishing in progress. VRF syetem - in progress.
No Image
Malakand
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 69.527 615.909 0 100% 82%
April - 2018
OPD, main building - finishing in progress. VRF syetem - in progress.
No Image
Malakand
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 69.527 615.909 0 100% 82%
March - 2018
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids opened, tender approval in process.
No Image
Malakand
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 54.598 600.98 0 100% 80%
February - 2018
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids opened , tender approval in process.
No Image
Malakand
549
(OG)
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 750.011 546.382 203.629 203.629 102 54.598 600.98 0 100% 80%
January - 2018
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids being invited.
No Image
549
(OG)
140814-Development activities in militancy hit areas of Koh-e-Daman, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 180.883 40.646 255.659 255.659 58 22.8 63.446 0 100% 35%
September - 2018
Work on all 20 Nos roads in progress (50% completed).
No Image
1) Ghareeb Abad (BT/rehabilitation of road)
2) Dandoo Pul (BT/rehabilitation of road)
3) Haji Abad Surizai Payan (BT/rehabilitation of road)
4) Musafir Abad (BT/rehabilitation of road)
5) Mama Khel UC 217 (BT/rehabilitation of road)
6) Gulshan Abad (BT/rehabilitation of road)
7) Dabal Pul to Agar Khel (BT/rehabilitation of road)
8) Roshan Kababi to Canal (BT/rehabilitation of road)
9) Badshan Khel Mera (BT/rehabilitation of road)
10) GHS Surizai Bala (BT/rehabilitation of road)
11) Surizai to Bdabeer (BT/rehabilitation of road)
12) Darwazgay to Mathani-1 (BT/rehabilitation of road)
13) Darwazgay to Mathani-2 (BT/rehabilitation of road)
14) Gulshan Abad Mathani (BT/rehabilitation of road)
15) Sa Khawra Mathani (BT/rehabilitation of road)
16) Nazim Muhammad Ali to Madar Khan House (BT/rehabilitation of road)
17) Ghazi Abad Aka Khel (BT/rehabilitation of road)
18) Adezi UC-61 (BT/rehabilitation of road)
19) Arat Baba to Passani (BT/rehabilitation of road)
20) Sarwari Muqbara Aza Khel (BT/rehabilitation of road)
549
(OG)
140814-Development activities in militancy hit areas of Koh-e-Daman, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 180.883 40.646 255.659 255.659 0 0 40.646 0 100% 22%
July - 2018
Work on all 20 Nos roads in progress (50% completed).
No Image
1) Ghareeb Abad (BT/rehabilitation of road)
2) Dandoo Pul (BT/rehabilitation of road)
3) Haji Abad Surizai Payan (BT/rehabilitation of road)
4) Musafir Abad (BT/rehabilitation of road)
5) Mama Khel UC 217 (BT/rehabilitation of road)
6) Gulshan Abad (BT/rehabilitation of road)
7) Dabal Pul to Agar Khel (BT/rehabilitation of road)
8) Roshan Kababi to Canal (BT/rehabilitation of road)
9) Badshan Khel Mera (BT/rehabilitation of road)
10) GHS Surizai Bala (BT/rehabilitation of road)
11) Surizai to Bdabeer (BT/rehabilitation of road)
12) Darwazgay to Mathani-1 (BT/rehabilitation of road)
13) Darwazgay to Mathani-2 (BT/rehabilitation of road)
14) Gulshan Abad Mathani (BT/rehabilitation of road)
15) Sa Khawra Mathani (BT/rehabilitation of road)
16) Nazim Muhammad Ali to Madar Khan House (BT/rehabilitation of road)
17) Ghazi Abad Aka Khel (BT/rehabilitation of road)
18) Adezi UC-61 (BT/rehabilitation of road)
19) Arat Baba to Passani (BT/rehabilitation of road)
20) Sarwari Muqbara Aza Khel (BT/rehabilitation of road)
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.438 99.704 1402.727 0.004 100% 100%
December - 2018
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion.
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.437 52.719 1355.742 0.004 100% 96%
November - 2018
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion.
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.437 52.719 1355.742 0.004 100% 96%
November - 2018
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion.
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.437 105.437 1408.46 0.004 100% 100%
April - 2019
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation).
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.438 105.438 1408.461 0.004 100% 100%
March - 2019
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation).
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.438 105.438 1408.461 0.004 100% 100%
March - 2019
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation).
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.438 105.438 1408.461 0.004 100% 100%
February - 2019
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion.(above allocation )
No Image
Peshawar
549
(OG)
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I).
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 1408.464 1303.023 105.437 105.437 105.438 104.567 1407.59 0.004 100% 100%
January - 2019
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion.(above allocation )
No Image
Peshawar