Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
17-05-13 | 30-06-18 | - | 12-04-16 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 43.438 | 589.82 | 0 | 100% |
79% December - 2017 |
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids being invited. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
17-05-13 | 30-06-18 | - | 12-04-16 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 43.5 | 589.882 | 0 | 100% |
79% September - 2017 |
OPD, main building - finishing in progress. Pre-qualification invited for VRF. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
17-05-13 | 30-06-18 | - | 12-04-16 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 0 | 546.382 | 0 | 100% |
73% August - 2017 |
OPD, main building - finishing in progress. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
17-05-13 | 30-06-18 | - | 12-04-16 | - | 750.011 | 546.382 | 203.629 | 203.629 | 0 | 0 | 546.382 | 0 | 100% |
73% July - 2017 |
OPD, main building - finishing in progress. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 43.438 | 589.82 | 0 | 100% |
79% November - 2017 |
OPD, main building - finishing in progress. Pre-qualification invited for VRF. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 43.438 | 589.82 | 0 | 100% |
79% October - 2017 |
OPD, main building - finishing in progress. Pre-qualification invited for VRF. |
No Image |
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 102 | 102 | 69.42 | 615.802 | 0 | 100% |
82% June - 2018 |
OPD, main building - finishing in progress. VRF syetem - in progress. |
No Image |
Malakand | |||||||||||||||||||
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 69.527 | 615.909 | 0 | 100% |
82% May - 2018 |
OPD, main building - finishing in progress. VRF syetem - in progress. |
No Image |
Malakand | |||||||||||||||||||
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 69.527 | 615.909 | 0 | 100% |
82% April - 2018 |
OPD, main building - finishing in progress. VRF syetem - in progress. |
No Image |
Malakand | |||||||||||||||||||
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 69.527 | 615.909 | 0 | 100% |
82% March - 2018 |
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids opened, tender approval in process. |
No Image |
Malakand | |||||||||||||||||||
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 54.598 | 600.98 | 0 | 100% |
80% February - 2018 |
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids opened , tender approval in process. |
No Image |
Malakand | |||||||||||||||||||
549 (OG) |
100428-Improvement and Standardization of DHQ Hospital Batkhela, Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 750.011 | 546.382 | 203.629 | 203.629 | 102 | 54.598 | 600.98 | 0 | 100% |
80% January - 2018 |
OPD, main building - finishing in progress. Pre-qualification approved for VRF component. Financial bids being invited. |
No Image |
549 (OG) |
140814-Development activities in militancy hit areas of Koh-e-Daman, District Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.883 | 40.646 | 255.659 | 255.659 | 58 | 22.8 | 63.446 | 0 | 100% |
35% September - 2018 |
Work on all 20 Nos roads in progress (50% completed). |
No Image |
1) Ghareeb Abad (BT/rehabilitation of road)
2) Dandoo Pul (BT/rehabilitation of road)
3) Haji Abad Surizai Payan (BT/rehabilitation of road)
4) Musafir Abad (BT/rehabilitation of road)
5) Mama Khel UC 217 (BT/rehabilitation of road)
6) Gulshan Abad (BT/rehabilitation of road)
7) Dabal Pul to Agar Khel (BT/rehabilitation of road)
8) Roshan Kababi to Canal (BT/rehabilitation of road)
9) Badshan Khel Mera (BT/rehabilitation of road)
10) GHS Surizai Bala (BT/rehabilitation of road)
11) Surizai to Bdabeer (BT/rehabilitation of road)
12) Darwazgay to Mathani-1 (BT/rehabilitation of road)
13) Darwazgay to Mathani-2 (BT/rehabilitation of road)
14) Gulshan Abad Mathani (BT/rehabilitation of road)
15) Sa Khawra Mathani (BT/rehabilitation of road)
16) Nazim Muhammad Ali to Madar Khan House (BT/rehabilitation of road)
17) Ghazi Abad Aka Khel (BT/rehabilitation of road)
18) Adezi UC-61 (BT/rehabilitation of road)
19) Arat Baba to Passani (BT/rehabilitation of road)
20) Sarwari Muqbara Aza Khel (BT/rehabilitation of road) | |||||||||||||||||||
549 (OG) |
140814-Development activities in militancy hit areas of Koh-e-Daman, District Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.883 | 40.646 | 255.659 | 255.659 | 0 | 0 | 40.646 | 0 | 100% |
22% July - 2018 |
Work on all 20 Nos roads in progress (50% completed). |
No Image |
1) Ghareeb Abad (BT/rehabilitation of road)
2) Dandoo Pul (BT/rehabilitation of road)
3) Haji Abad Surizai Payan (BT/rehabilitation of road)
4) Musafir Abad (BT/rehabilitation of road)
5) Mama Khel UC 217 (BT/rehabilitation of road)
6) Gulshan Abad (BT/rehabilitation of road)
7) Dabal Pul to Agar Khel (BT/rehabilitation of road)
8) Roshan Kababi to Canal (BT/rehabilitation of road)
9) Badshan Khel Mera (BT/rehabilitation of road)
10) GHS Surizai Bala (BT/rehabilitation of road)
11) Surizai to Bdabeer (BT/rehabilitation of road)
12) Darwazgay to Mathani-1 (BT/rehabilitation of road)
13) Darwazgay to Mathani-2 (BT/rehabilitation of road)
14) Gulshan Abad Mathani (BT/rehabilitation of road)
15) Sa Khawra Mathani (BT/rehabilitation of road)
16) Nazim Muhammad Ali to Madar Khan House (BT/rehabilitation of road)
17) Ghazi Abad Aka Khel (BT/rehabilitation of road)
18) Adezi UC-61 (BT/rehabilitation of road)
19) Arat Baba to Passani (BT/rehabilitation of road)
20) Sarwari Muqbara Aza Khel (BT/rehabilitation of road) | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.438 | 99.704 | 1402.727 | 0.004 | 100% |
100% December - 2018 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion. |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.437 | 52.719 | 1355.742 | 0.004 | 100% |
96% November - 2018 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion. |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.437 | 52.719 | 1355.742 | 0.004 | 100% |
96% November - 2018 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.210 m required for completion. |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.437 | 105.437 | 1408.46 | 0.004 | 100% |
100% April - 2019 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation). |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.438 | 105.438 | 1408.461 | 0.004 | 100% |
100% March - 2019 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation). |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.438 | 105.438 | 1408.461 | 0.004 | 100% |
100% March - 2019 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion (above allocation). |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.438 | 105.438 | 1408.461 | 0.004 | 100% |
100% February - 2019 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion.(above allocation ) |
No Image |
Peshawar | |||||||||||||||||||
549 (OG) |
20889-F/S, Planning, Designing and Construction of Central Prison, Peshawar (Phase-I). |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1408.464 | 1303.023 | 105.437 | 105.437 | 105.438 | 104.567 | 1407.59 | 0.004 | 100% |
100% January - 2019 |
8 blocks - Block-1, 2 and 7 - basement column in progress. Block-3 - 25 Nos piles completed. Block-4 - GF slab in progress (1st portion). Block-5 and 6 - structure completed. Block-7 - pile cap in progress. Block-8 - piles cap completed. Demand Rs.120 m required for completion.(above allocation ) |
No Image |
Peshawar | |||||||||||||||||||
Pages : 1 |