Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
538 (OG) |
160599-Uplift and Development of hillstations in Malakand Division. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.589 | 11.271 | 0 | 0 | 0 | 0 | 11.271 | 40.318 | - |
22% September - 2018 |
Work order issued. Site not yet handed over. Land acquisition under process. Land payment Rs.11.271 m made. Site survey in progress. |
No Image |
Construction of Park at Shahida Sar PK-78 | |||||||||||||||||||
538 (OG) |
160599-Uplift and Development of hillstations in Malakand Division. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 51.589 | 11.271 | 0 | 0 | 0 | 0 | 11.271 | 40.318 | - |
22% July - 2018 |
Work order issued. Site not yet handed over. Land acquisition under process. Land payment Rs.11.271 m made. Site survey in progress. |
No Image |
Construction of Park at Shahida Sar PK-78 | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
28-01-13 | - | - | 08-11-12 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 25 | 872.806 | 249.928 | 78% |
76% December - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 13.995 | 861.801 | 249.928 | 78% |
75% November - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 0 | 847.806 | 249.928 | 78% |
74% October - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
28-01-13 | - | - | 08-11-12 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 0 | 847.806 | 249.928 | 78% |
74% September - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
28-01-13 | - | - | 08-11-12 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 0 | 847.806 | 249.928 | 78% |
74% August - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
28-01-13 | - | - | 08-11-12 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 0 | 847.806 | 249.928 | 78% |
74% July - 2017 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 50 | 50 | 897.806 | 249.928 | 78% |
78% June - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 50 | 50 | 897.806 | 249.928 | 78% |
78% May - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 50 | 50 | 897.806 | 249.928 | 78% |
78% April - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 37.5 | 37.5 | 885.306 | 249.928 | 78% |
77% March - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress.
Demand Rs. __________ M |
No Image |
H | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 37.5 | 37.5 | 885.306 | 249.928 | 78% |
77% February - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress.
Demand Rs. __________ M |
No Image |
Hayatabad Peshawar
Main Building ( 297380 sft )
Nurse Hostel (13457 sft )
Paramedics Hostel (
Doctorsd Hostel
Doctors Flats
Masjid Building
Dev Works
Guard rooms
HVAC | |||||||||||||||||||
538 (OG) |
110004-Establishment of Fountain House in Peshawar. |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1147.734 | 847.806 | 50 | 50 | 25 | 25 | 872.806 | 249.928 | 78% |
76% January - 2018 |
Main building - nurses hostel, paramedic hostel, doctors hostel, doctors flat, boundary wall in progress, tube well boring completed. HVAC ducting in progress. |
No Image |
Hayatabad Peshawar | |||||||||||||||||||
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
538 (OG) |
160599-Uplift and Development of hillstations in Malakand Division. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
538 (OG) |
160599-Uplift and Development of hillstations in Malakand Division. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1500 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
DCE Submitted. |
No Image |
538 (New) |
200073-Reconstruction of Damaged School in Merged Districts (AIP) |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
DCE Submitted. |
No Image |
Pages : 1 |