Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, February - 2020, March - 2020, April - 2020, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
510
(OG)
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts".
Mardan
30-11--1 30-11--1 - 30-11--1 - 250 12.112 0 0 0 0 12.112 237.888 - 5%
September - 2018
SS in progress.
No Image
Mardan
510
(OG)
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts".
Mardan
30-11--1 30-11--1 - 30-11--1 - 250 12.112 0 0 0 0 12.112 237.888 - 5%
July - 2018
Excavation in progress.
No Image
Mardan
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
December - 2019
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
November - 2019
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
October - 2019
No Image
510
(OG)
195113-Development of Play Areas in Schools of Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 238.2 220.32 0 0 0 0 220.32 0 - -
October - 2020
No Image
510
(OG)
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts".
Provincial
30-11--1 30-11--1 - 30-11--1 - 247 0 0.001 0.001 0 0 0 0 - -
September - 2018
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
September - 2019
No Image
510
(OG)
195113-Development of Play Areas in Schools of Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 238.2 220.32 0 0 0 0 220.32 0 - -
September - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
August - 2019
No Image
510
(OG)
195113-Development of Play Areas in Schools of Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 238.2 220.32 0 0 0 0 220.32 0 - -
August - 2020
No Image
510
(OG)
140301-F/S & Master Planning for Construction of "Model Anti Terrorism Courts".
Provincial
30-11--1 30-11--1 - 30-11--1 - 247 0 0.001 0.001 0 0 0 0 - -
July - 2018
No Image
510
(OG)
195113-Development of Play Areas in Schools of Merged Areas (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 238.2 220.32 0 0 0 0 220.32 0 -
July - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
May - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
April - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
March - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
February - 2020
No Image
510
(OG)
140265-F/S & Construction of School of Investigation and Intelligence for Khyber Pakhtunkhwa (Phase-I)
Provincial
30-11--1 30-11--1 - 30-11--1 - 185.18 115.18 70 70 0 0 115.18 0 - -
January - 2020
No Image
Pages : 1