Progressive Review for the month(s) of : January - 2020, January - 2018, February - 2020, February - 2018, March - 2020, March - 2018, April - 2020, April - 2018, May - 2020, May - 2018, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, December - 2019, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 146.949 20 3 3 3 3 23 123.949 16% 16%
September - 2018
Basement, GF roof laid. FF cloumn laid.
No Image
1) Havelian
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 146.949 20 0 0 0 0 20 126.949 - 14%
July - 2018
Basement, GF roof laid. FF cloumn laid.
No Image
1) Havelian
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 332.616 204.504 4 4 4 4 208.504 124.112 63% 63%
September - 2018
Daraban - main building GF/FF roof laid. Demand Rs.85 m. Paharpur - tile of flooring in progress.
No Image
1) Tehsil Daraban
2) Tehsil Paharpur
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 332.616 204.504 0 0 0 0 204.504 128.112 - 61%
July - 2018
Daraban - main building GF/FF roof laid. Demand Rs.85 m. Paharpur - tile of flooring in progress.
No Image
1) Tehsil Daraban
2) Tehsil Paharpur
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Hangu
30-11--1 30-11--1 - 30-11--1 - 191.864 28.83 3 3 3 3 31.83 160.034 17% 17%
September - 2018
Main building - in progress. BW completed. Revised DCE approved.
No Image
Judicial Complex at Hangu
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Hangu
30-11--1 30-11--1 - 30-11--1 - 191.864 28.83 0 0 0 0 28.83 163.034 - 15%
July - 2018
Main building - in progress. BW completed. Revised DCE approved.
No Image
Judicial Complex at Hangu
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Mansehra
30-11--1 30-11--1 - 30-11--1 - 102 11.561 0 0 0 0 11.561 90.439 - 11%
September - 2018
Foundation and plinth in progress.
No Image
Tehsil Judicial Complex, Oghi Manshera
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Mansehra
30-11--1 30-11--1 - 30-11--1 - 102 11.561 0 0 0 0 11.561 90.439 - 11%
July - 2018
Foundation and plinth in progress.
No Image
Tehsil Judicial Complex, Oghi Manshera
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
- - - 29-12-15 - 95.654 0 5 5 2.5 0.19 0.19 90.654 5% 0%
December - 2017
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 0 0 90.654 5% -
November - 2017
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 0 0 90.654 5% -
October - 2017
Work order issued. Demolitaio of the existing BHU in progress. Modified DCE submitted to client deptt.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
- - - 29-12-15 - 95.654 0 5 5 2.5 0 0 90.654 5% -
September - 2017
Work order issued. Demolitaio of the existing BHU in progress. Modified DCE submitted to client deptt.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
- - - 29-12-15 - 95.654 0 5 5 2.5 0 0 90.654 5% -
August - 2017
Work order issued. NOC granted for demolition of existing building. Auction under process.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
- - - 29-12-15 - 95.654 0 5 5 2.5 0 0 90.654 5% -
July - 2017
Work order issued. NOC for demolition of existing building is awaited.
No Image
PK-01
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 5 5 5 90.654 5% 5%
June - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 5 5 5 90.654 5% 5%
May - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 2.5 2.5 90.654 5% 3%
April - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 2.5 2.5 90.654 5% 3%
March - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 2.5 2.5 90.654 5% 3%
February - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
PK 6
Main Building-2 storey- (labor Room , OT Block , OPD , Wards , Dental Block & Morturay )
508
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 0 5 5 2.5 0.19 0.19 90.654 5% 0%
January - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
PK-06, Peshawar
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
December - 2019
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
November - 2019
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
October - 2019
No Image
508
(OG)
195105-Provision of Basic and Missing Facilities through Parent Teacher Committee (PTCs) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 3869.42 1786.903 0 0 0 0 1786.903 0 - -
October - 2020
No Image
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Provincial
30-11--1 30-11--1 - 30-11--1 - 818.029 362.37 25 25 0 0 362.37 0 - -
September - 2018
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
September - 2019
No Image
508
(OG)
195105-Provision of Basic and Missing Facilities through Parent Teacher Committee (PTCs) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 3869.42 1786.903 0 0 0 0 1786.903 0 - -
September - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
August - 2019
No Image
508
(OG)
195105-Provision of Basic and Missing Facilities through Parent Teacher Committee (PTCs) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 3869.42 1786.903 0 0 0 0 1786.903 0 - -
August - 2020
No Image
508
(OG)
140296-F/S and Construction of Tehsil Judicial Complexes in 5 Selected Districts on Priority Basis (Paharpur, Draband, Oghi, Havelian and Hangu).
Provincial
30-11--1 30-11--1 - 30-11--1 - 818.029 362.37 25 25 0 0 362.37 0 - -
July - 2018
No Image
508
(OG)
195105-Provision of Basic and Missing Facilities through Parent Teacher Committee (PTCs) (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 - 3869.42 1786.903 0 0 0 0 1786.903 0 -
July - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
May - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
April - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
March - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
February - 2020
No Image
508
(OG)
130378-Special Development Support for Khyber Pakhtunkhwa Police,SDSP-IV.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1048 493.088 80 80 0 0 493.088 0 - -
January - 2020
No Image