Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 3 | 3 | 3 | 0 | 0 | 278.386 | 1% |
- September - 2018 |
Work order issued. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 0 | 0 | 0 | 0 | 0 | 0 | 281.386 | - |
- July - 2018 |
Work order issued. |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 3 | 3 | 3 | 3 | 3.3 | 99.982 | 3% |
3% September - 2018 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 0.3 | 0 | 0 | 0 | 0 | 0.3 | 102.982 | - |
0% July - 2018 |
Focal person (XEN Abbottabad).
Work order issued on 05/09/2017. Supervising consultant just selected. Layout given. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- September - 2018 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- July - 2018 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- December - 2019 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- November - 2019 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- October - 2019 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- September - 2019 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- August - 2019 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- May - 2020 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- April - 2020 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- March - 2020 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- February - 2020 |
No Image | |
506 (OG) |
140836-Construction of Police Station at Asbanr and Re-construction of Police Check Posts at Miskini and Kambat, Dir (Lower), |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 64 | 6 | 6 | 0 | 0 | 64 | 0 | - |
- January - 2020 |
No Image | |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 13.071 | 9.068 | 3.819 | 19.918 | 0 | 100% |
80% December - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 13.071 | 9.068 | 3.819 | 19.918 | 0 | 100% |
80% December - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 13.071 | 9.068 | 0 | 16.099 | 0 | 100% |
64% October - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 13.071 | 6 | 1.578 | 17.677 | 0 | 100% |
71% September - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 13.071 | 0 | 0 | 16.099 | 0 | 100% |
64% August - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 0 | 0 | 0 | 16.099 | 0 | 100% |
64% July - 2020 |
08- Packages
work in progress on all compoents. |
No Image |
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 11.07 | 11.07 | 5.165 | 21.264 | 0 | 100% |
85% May - 2021 |
08- Packages
20 Units work in progress on all compoents. |
No Image |
Package 1
1 GPS Aziz Ur Rehaman
2 GGPS Baz Gul Killi
3 GGPS Hassan Khan
Package 2
1 GPS Zarin Khel
2 GGPS M. Younas
3 GGPS Sawar Khan
Package 3
1 GPS Awal SHer
2 GPS Mohd. Gul
Package 4
1 GGPS Qarar Khan
2 GHSS Sama Badaber
3 GGMS Mir Haider
Package 5
1 GGMS Sadi Khan
2 GGHS War Khan
3 GGPS Hakeem Khan
Package 6
1 GHS Faridi
2 GPS Faridi No.3
3 GGPS Juma khan
Package 7
1 GGPS Abdur Rasheed
2 GHS Said Azam
Package 8
1 GHS Kandow | |||||||||||||||||||
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 11.07 | 11.07 | 5.165 | 21.264 | 0 | 100% |
85% April - 2021 |
08- Packages
20 Units work in progress on all compoents. |
No Image |
Package 1
1 GPS Aziz Ur Rehaman
2 GGPS Baz Gul Killi
3 GGPS Hassan Khan
Package 2
1 GPS Zarin Khel
2 GGPS M. Younas
3 GGPS Sawar Khan
Package 3
1 GPS Awal SHer
2 GPS Mohd. Gul
Package 4
1 GGPS Qarar Khan
2 GHSS Sama Badaber
3 GGMS Mir Haider
Package 5
1 GGMS Sadi Khan
2 GGHS War Khan
3 GGPS Hakeem Khan
Package 6
1 GHS Faridi
2 GPS Faridi No.3
3 GGPS Juma khan
Package 7
1 GGPS Abdur Rasheed
2 GHS Said Azam
Package 8
1 GHS Kandow | |||||||||||||||||||
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 11.07 | 11.07 | 5.165 | 21.264 | 0 | 100% |
85% March - 2021 |
08- Packages
20 Units work in progress on all compoents. |
No Image |
Package 1
1 GPS Aziz Ur Rehaman
2 GGPS Baz Gul Killi
3 GGPS Hassan Khan
Package 2
1 GPS Zarin Khel
2 GGPS M. Younas
3 GGPS Sawar Khan
Package 3
1 GPS Awal SHer
2 GPS Mohd. Gul
Package 4
1 GGPS Qarar Khan
2 GHSS Sama Badaber
3 GGMS Mir Haider
Package 5
1 GGMS Sadi Khan
2 GGHS War Khan
3 GGPS Hakeem Khan
Package 6
1 GHS Faridi
2 GPS Faridi No.3
3 GGPS Juma khan
Package 7
1 GGPS Abdur Rasheed
2 GHS Said Azam
Package 8
1 GHS Kandow | |||||||||||||||||||
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 11.07 | 11.07 | 5.165 | 21.264 | 0 | 100% |
85% February - 2021 |
08- Packages
20 Units work in progress on all compoents. |
No Image |
Package 1
1 GPS Aziz Ur Rehaman
2 GGPS Baz Gul Killi
3 GGPS Hassan Khan
Package 2
1 GPS Zarin Khel
2 GGPS M. Younas
3 GGPS Sawar Khan
Package 3
1 GPS Awal SHer
2 GPS Mohd. Gul
Package 4
1 GGPS Qarar Khan
2 GHSS Sama Badaber
3 GGMS Mir Haider
Package 5
1 GGMS Sadi Khan
2 GGHS War Khan
3 GGPS Hakeem Khan
Package 6
1 GHS Faridi
2 GPS Faridi No.3
3 GGPS Juma khan
Package 7
1 GGPS Abdur Rasheed
2 GHS Said Azam
Package 8
1 GHS Kandow | |||||||||||||||||||
506 (OG) |
191337-170194 - Construction of Additional Class Room / Missing Facilities in FR Peshawar. [MA] |
FR Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25 | 16.099 | 13.071 | 11.07 | 11.07 | 3.819 | 19.918 | 0 | 100% |
80% January - 2021 |
08- Packages
work in progress on all compoents. |
No Image |
Package 1
1 GPS Aziz Ur Rehaman
2 GGPS Baz Gul Killi
3 GGPS Hassan Khan
Package 2
1 GPS Zarin Khel
2 GGPS M. Younas
3 GGPS Sawar Khan
Package 3
1 GPS Awal SHer
2 GPS Mohd. Gul
Package 4
1 GGPS Qarar Khan
2 GHSS Sama Badaber
3 GGMS Mir Haider
Package 5
1 GGMS Sadi Khan
2 GGHS War Khan
3 GGPS Hakeem Khan
Package 6
1 GHS Faridi
2 GPS Faridi No.3
3 GGPS Juma khan
Package 7
1 GGPS Abdur Rasheed
2 GHS Said Azam
Package 8
1 GHS Kandow | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 5.125 | 4 | 4 | 4 | 4 | 9.125 | 84.979 | 10% |
10% September - 2018 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 5.125 | 0 | 0 | 0 | 0 | 5.125 | 88.979 | - |
5% July - 2018 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1469.574 | 0 | 20 | 20 | 0 | 0 | 0 | 1449.574 | 1% |
- September - 2018 |
No Image | |
506 (OG) |
130446-F/S for Assessment of residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1469.574 | 0 | 20 | 20 | 0 | 0 | 0 | 1449.574 | 1% |
- July - 2018 |
No Image | |
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 342.221 | 0 | 0 | 0 | 0 | 0 | 0 | 342.221 | - |
- September - 2018 |
Compact RFP floated for selection of consultant. Proposal invited on 31/05/2017 (focal person XEN Abbottabad). Supervising consultant just selected. Land acquisition under process. |
No Image |
Construction of Judicial Complex at Behrain Swat | |||||||||||||||||||
506 (OG) |
130446-F/S for Assessment of Residential requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 342.221 | 0 | 0 | 0 | 0 | 0 | 0 | 342.221 | - |
- July - 2018 |
Compact RFP floated for selection of consultant. Proposal invited on 31/05/2017 (focal person XEN Abbottabad). Supervising consultant just selected. Land acquisition under process. |
No Image |
Construction of Judicial Complex at Behrain Swat | |||||||||||||||||||
Pages : 1 |