Progressive Review for the month(s) of : January - 2020, January - 2021, February - 2020, February - 2021, March - 2020, March - 2021, April - 2021, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 27.799 18.524 0 5.381 0 100% 18%
December - 2020
Work order issued
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 27.799 18.524 0 5.381 0 100% 18%
December - 2020
Work order issued
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 27.799 18.524 0 5.381 0 100% 18%
October - 2020
Work order approval awaited.
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 27.799 12 0 5.381 0 100% 18%
September - 2020
Work order approval awaited.
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 27.799 0 0 5.381 0 100% 18%
August - 2020
Re-Tender on 22/09/20
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 0 0 0 5.381 0 100% 18%
July - 2020
No Image
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 0 27.799 23.162 23.162 1.903 1.903 2.201 93% 6%
May - 2021
02 Units work in progress 1 DPC level 2 Lintel Level Cannot be completed due to late site identificaiton
No Image
1 GMS to GHS Mohd. Shah Killi
2 GGPS to GGMS Lal zamir Afridi
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 0 27.799 23.162 23.162 1.903 1.903 2.201 93% 6%
April - 2021
02 Units work in progress 1 DPC level 2 Lintel Level Cannot be completed due to late site identificaiton
No Image
1 GMS to GHS Mohd. Shah Killi
2 GGPS to GGMS Lal zamir Afridi
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 0 27.799 23.162 23.162 1.903 1.903 2.201 93% 6%
March - 2021
02 Units work in progress 1 DPC level 2 Lintel Level Cannot be completed due to late site identificaiton
No Image
1 GMS to GHS Mohd. Shah Killi
2 GGPS to GGMS Lal zamir Afridi
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 0 27.799 23.162 23.162 1.903 1.903 2.201 93% 6%
February - 2021
02 Units work in progress 1 DPC level 2 Lintel Level Cannot be completed due to late site identificaiton
No Image
1 GMS to GHS Mohd. Shah Killi
2 GGPS to GGMS Lal zamir Afridi
505
(OG)
191336-170193 - Upgradation of Educational Institutions in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 30 5.381 27.799 23.162 23.162 0 5.381 0 100% 18%
January - 2021
Work order issued
No Image
1 GMS to GHS Mohd. Shah Killi
2 GGPS to GGMS Lal zamir Afridi
505
(OG)
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 859 638.426 22.361 22.361 11.18 11.18 649.606 198.213 77% 76%
September - 2018
Main building, bar room, mosque, shed, tube well 85% completed. Balance work - work started.
No Image
Judicial Complex Haripur
505
(OG)
110457-Construction of Judicial Complex and Construction of Lawyers shed in Judicial Complex, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 859 638.426 22.361 22.361 0 0 638.426 198.213 77% 74%
July - 2018
Main building, bar room, mosque, shed, tube well 85% completed. Balance work - work started.
No Image
Judicial Complex Haripur
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
December - 2019
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
November - 2019
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
October - 2019
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
September - 2019
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
August - 2019
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
May - 2020
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
April - 2020
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
March - 2020
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
February - 2020
No Image
505
(OG)
160432-Joint Police Training Center (Phase-II) at Hakeem Abad Nowshera through UNDP (INL Assisted).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0.001 0 0.001 0.001 0 0 0 0 - -
January - 2020
No Image