Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 118.51 | 42 | 42 | 30 | 21.865 | 140.375 | 123.112 | 57% |
49% December - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 118.51 | 42 | 42 | 12 | 12 | 130.51 | 123.112 | 57% |
46% November - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 283.622 | 118.51 | 42 | 42 | 12 | 12 | 130.51 | 123.112 | 57% |
46% November - 2018 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 232.812 | 118.51 | 42 | 42 | 37.5 | 33.825 | 152.335 | 72.302 | 69% |
65% April - 2019 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 232.812 | 118.51 | 42 | 42 | 37.5 | 29.992 | 148.502 | 72.302 | 69% |
64% March - 2019 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 232.812 | 118.51 | 42 | 42 | 37.5 | 29.992 | 148.502 | 72.302 | 69% |
64% March - 2019 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 232.812 | 118.51 | 42 | 42 | 30 | 24.962 | 143.472 | 72.302 | 69% |
62% February - 2019 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
151058-Establishment of Government Degree College in PK-21. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 232.812 | 118.51 | 42 | 42 | 30 | 23.191 | 141.701 | 72.302 | 69% |
61% January - 2019 |
Main building - foundation, BW, developmental work in progress. |
No Image |
PK-21 Charsadda | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 17.5 | 17.5 | 117.8 | 53.991 | 76% |
53% December - 2019 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 17.5 | 17.5 | 117.8 | 53.991 | 76% |
53% November - 2019 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 17.5 | 17.5 | 117.8 | 53.991 | 76% |
53% October - 2019 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 17.5 | 0 | 100.3 | 53.991 | 76% |
45% September - 2019 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 0 | 0 | 100.3 | 53.991 | 76% |
45% August - 2019 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 70 | 52.289 | 152.589 | 53.991 | 76% |
68% May - 2020 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 70 | 52.289 | 152.589 | 53.991 | 76% |
68% April - 2020 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 70 | 52.289 | 152.589 | 53.991 | 76% |
68% March - 2020 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 70 | 52.289 | 152.589 | 53.991 | 76% |
68% February - 2020 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
150052-Re-Construction of Building for GCMS(Boys), D.I Khan |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 224.291 | 100.3 | 70 | 70 | 70 | 18.521 | 118.821 | 53.991 | 76% |
53% January - 2020 |
Admin block - flooring completed. BW, OHT & Pumping chamber- completed. Academic block, in progress. |
No Image |
GCMS Boys DI.Khan | |||||||||||||||||||
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 74.157 | 21.5 | 21.5 | 21.5 | 12.777 | 86.934 | 11.778 | 89% |
81% September - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 107.435 | 74.157 | 0 | 0 | 0 | 0 | 74.157 | 33.278 | - |
69% July - 2018 |
Work in progress on 6/6 units. |
No Image |
Central Prison Haripur (remaining BW/interview shed with allied facility/watch tower on P/Wall/warden barrack/kitchen/second armor block/water reservoir/drain) | |||||||||||||||||||
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% September - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.277 | 44.277 | 0 | 0 | 0 | 0 | 44.277 | 0 | - |
100% July - 2018 |
Completed & H/O. |
No Image |
Sub Jail Karak | |||||||||||||||||||
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 43 | 43 | 21.5 | 0 | 71.777 | 28.223 | 80% |
50% September - 2018 |
No Image | |
455 (OG) |
120802-Execution of Additional Works at Central Prison Haripur and Sub Jail Karak. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 143 | 71.777 | 43 | 43 | 0 | 0 | 71.777 | 28.223 | 80% |
50% July - 2018 |
No Image | |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% December - 2020 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% December - 2020 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% October - 2020 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% September - 2020 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0 | 26.579 | 0 | 100% |
95% August - 2020 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 2.39 | 2.39 | 0.39 | 26.969 | 0 | 100% |
97% May - 2021 |
06- Units
1. Completed & H/O
2. Completed & H/O
3. Finishing
4. M.Buld: Completed
5. Finsihing
6. Completed & H/O |
No Image |
1 GGPS Sarwar Shah
2 GPS Jawakai
3 GPS Warzha SHingi
4 GPS Chargoali
5 GMS Nanak Raghzai
6 GGPS Azam Khan | |||||||||||||||||||
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% April - 2021 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
1 GGPS Sarwar Shah
2 GPS Jawakai
3 GPS Warzha SHingi
4 GPS Chargoali
5 GMS Nanak Raghzai
6 GGPS Azam Khan | |||||||||||||||||||
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% March - 2021 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
1 GGPS Sarwar Shah
2 GPS Jawakai
3 GPS Warzha SHingi
4 GPS Chargoali
5 GMS Nanak Raghzai
6 GGPS Azam Khan | |||||||||||||||||||
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% February - 2021 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
1 GGPS Sarwar Shah
2 GPS Jawakai
3 GPS Warzha SHingi
4 GPS Chargoali
5 GMS Nanak Raghzai
6 GGPS Azam Khan | |||||||||||||||||||
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.907 | 26.579 | 3.668 | 3.668 | 3.668 | 0.762 | 27.341 | 0 | 100% |
98% January - 2021 |
06- components
Completed & H/O =04
In finishing stage =02 |
No Image |
1 GGPS Sarwar Shah
2 GPS Jawakai
3 GPS Warzha SHingi
4 GPS Chargoali
5 GMS Nanak Raghzai
6 GGPS Azam Khan | |||||||||||||||||||
455 (OG) |
191371-080116 - Provision of 6 Nos. buildings for shelter less primary schools in SWA [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.267 | 24.599 | 3.668 | 0 | 0 | 0 | 24.599 | 0 |
July - 2020 |
No Image | ||
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
- | 30-06-18 | - | - | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
- | 30-06-18 | - | - | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
- | 30-06-18 | - | - | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
- | 30-06-18 | - | - | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
No Image | |
455 (New) |
170611-Acquisition of Land for Food Grain Godowns in District Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 23 | 0 | 23 | 23 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
No Image | |