Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 35.12 | 35.12 | 35.12 | 26.108 | 53.608 | 21.087 | 75% |
64% December - 2018 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 24.5 | 24.5 | 24.5 | 16.5 | 44 | 31.707 | 62% |
53% November - 2018 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 24.5 | 24.5 | 24.5 | 16.5 | 44 | 31.707 | 62% |
53% November - 2018 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 47.71 | 47.71 | 47.71 | 30.228 | 57.728 | 8.497 | 90% |
69% April - 2019 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 35.12 | 35.12 | 35.12 | 30.228 | 57.728 | 21.087 | 75% |
69% March - 2019 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 35.12 | 35.12 | 35.12 | 30.228 | 57.728 | 21.087 | 75% |
69% March - 2019 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 35.12 | 35.12 | 35.12 | 30.228 | 57.728 | 21.087 | 75% |
69% February - 2019 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 83.707 | 27.5 | 35.12 | 35.12 | 35.12 | 30.228 | 57.728 | 21.087 | 75% |
69% January - 2019 |
Main building - GF plastering in progress. |
No Image |
Public Library Buner | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% December - 2018 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% November - 2018 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% November - 2018 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% April - 2019 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% March - 2019 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% March - 2019 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% February - 2019 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.502 | 92.257 | 5.252 | 5.252 | 5.252 | 5.252 | 97.509 | 0 | 100% |
100% January - 2019 |
Main building - flooring in progress. Guest house - finishing in progress. |
No Image |
Public Library at Charsadda PK-17 | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
- | - | - | 18-09-17 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- December - 2017 |
Tender re-called on 24/01/2018. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
- | - | - | 18-09-17 | - | 23.039 | 0 | 10 | 10 | 0 | 0 | 0 | 13.039 | 43% |
- September - 2017 |
Procurement under process. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
- | - | - | - | Line Deptt | 25 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE submitted to Food Deptt. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
- | - | - | - | Line Deptt | 25 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
DCE under preparation. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- November - 2017 |
Tender under process. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 0 | 0 | 0 | 13.039 | 43% |
- October - 2017 |
Tender under process. |
No Image |
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- June - 2018 |
Excavation in progress. |
No Image |
Hangu | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- May - 2018 |
Work order issued. |
No Image |
Hangu | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- April - 2018 |
Work order issued. |
No Image |
Hangu | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- March - 2018 |
Work order issued. |
No Image |
Hangu | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- February - 2018 |
Financial bids opened on 22/02/2018, approval under process. |
No Image |
Hangu | |||||||||||||||||||
451 (New) |
170607-Construction of Food Grain Godowns of 500 Ton Capacity in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.039 | 0 | 10 | 10 | 2.5 | 0 | 0 | 13.039 | 43% |
- January - 2018 |
Tender re-called on 24/01/2018. |
No Image |
Hangu | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 15 | 15 | 15 | 9.407 | 19.407 | 23.516 | 52% |
40% December - 2018 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 10 | 10 | 10 | 9.407 | 19.407 | 28.516 | 41% |
40% November - 2018 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 10 | 10 | 10 | 9.407 | 19.407 | 28.516 | 41% |
40% November - 2018 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 21.768 | 21.768 | 21.768 | 18.516 | 28.516 | 16.748 | 65% |
59% April - 2019 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 18.516 | 18.516 | 18.516 | 14.918 | 24.918 | 20 | 59% |
51% March - 2019 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 18.516 | 18.516 | 18.516 | 14.918 | 24.918 | 20 | 59% |
51% March - 2019 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 15 | 15 | 15 | 14.195 | 24.195 | 23.516 | 52% |
50% February - 2019 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.516 | 10 | 15 | 15 | 15 | 9.407 | 19.407 | 23.516 | 52% |
40% January - 2019 |
Main building - in progress. BW, guard room foundation in progress. |
No Image |
Public Library at Ghazi, Haripur | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 31.248 | 31.248 | 31.248 | 5.826 | 53.076 | 20.013 | 80% |
54% December - 2018 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 13.248 | 13.248 | 13.248 | 5.386 | 52.636 | 38.013 | 61% |
53% November - 2018 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 13.248 | 13.248 | 13.248 | 5.386 | 52.636 | 38.013 | 61% |
53% November - 2018 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 53.51 | 53.51 | 53.51 | 22.025 | 69.275 | 0 | 100% |
70% April - 2019 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 53.51 | 53.51 | 53.51 | 21.635 | 68.885 | 0 | 100% |
70% March - 2019 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 53.51 | 53.51 | 53.51 | 21.635 | 68.885 | 0 | 100% |
70% March - 2019 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 31.248 | 31.248 | 31.248 | 21.62 | 68.87 | 20.013 | 80% |
70% February - 2019 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 98.511 | 47.25 | 31.248 | 31.248 | 31.248 | 15.795 | 63.045 | 20.013 | 80% |
64% January - 2019 |
Library - GF roof laid. FF roofing in progress. Rest house - upto roof level. |
No Image |
Public Library Mansehra PK-53 (1 unit) | |||||||||||||||||||
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 103.507 | 136.24 | 136.24 | 0 | 0 | 103.507 | 0 | 100% |
100% December - 2018 |
No Image | |
451 (New) |
190095-Rehabilitation & Strengthening of government colleges in District Swat and Tank. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 103.507 | 136.24 | 136.24 | 0 | 0 | 103.507 | 0 | 100% |
100% November - 2018 |
No Image | |
451 (OG) |
130187-Establishment of Pubic Libraries (Phase-III). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10 | 103.507 | 136.24 | 136.24 | 0 | 0 | 103.507 | 0 | 100% |
100% November - 2018 |
No Image | |
451 (New) |
190095-Rehabilitation & Strengthening of government colleges in District Swat and Tank. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
451 (New) |
190095-Rehabilitation & Strengthening of government colleges in District Swat and Tank. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
Pages : 1 2 |