Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, February - 2021, February - 2020, March - 2021, March - 2020, April - 2021, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019, December - 2020,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
December - 2019
Work order issued.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 0 0 0 0 0 1.5 - -
November - 2019
Work order issued.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 0 0 0 0 0 1.5 - -
October - 2019
Work order issued.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 0 0 0 0 0 1.5 - -
September - 2019
Work order issued.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 0 0 0 0 0 1.5 - -
August - 2019
Work order issued.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
May - 2020
Completed.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
April - 2020
Completed.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
March - 2020
Completed.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
February - 2020
Completed.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1 1 1 0.932 0.932 0.5 67% 62%
January - 2020
Completed.
No Image
Hangu
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0 0 0 0 0 7.364 - -
September - 2018
Out of 5 units, 2 in progress, 1 site not handed over, 1 tender called on 02/05/2018.
No Image
1) Masjid Targar Bannu City (improvement)
2) Masjid Dr. Gul Jahan Shah Kotka Gul Ahmed Shah Sheikhan Bannu (improvement)
3) Masjid Mufti Gohar Ali Shah Kotka Saddat Bannu (improvement)
4) Masjid Sattar Mal Mandi Bannu City (improvement)
5) Masjid At Titer Khel Jandu Khe Bannu (improvement)
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0 0 0 0 0 7.364 - -
July - 2018
Out of 5 units, 2 in progress, 1 site not handed over, 1 tender called on 02/05/2018.
No Image
1) Masjid Targar Bannu City (improvement)
2) Masjid Dr. Gul Jahan Shah Kotka Gul Ahmed Shah Sheikhan Bannu (improvement)
3) Masjid Mufti Gohar Ali Shah Kotka Saddat Bannu (improvement)
4) Masjid Sattar Mal Mandi Bannu City (improvement)
5) Masjid At Titer Khel Jandu Khe Bannu (improvement)
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2019
DCE Rs.9.928 (M) submitted to SO Dev: Auqaf Hajj & Minority Affairs. Dt 05/09/19 DDWP will be held on 03/12/19.
No Image
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2019
DCE Rs.9.928 (M) submitted to SO Dev: Auqaf Hajj & Minority Affairs. Dt 05/09/19 DDWP will be held on 03/12/19.
No Image
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 8.75 0 0 0 0 8.75 13.25 - 40%
September - 2018
Out of 3 units, all in progress.
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba, Buner PK-79 (construction of students hostel)
2) Jamia Masjid Baro Masjid village Kalpani, Buner PK-78 (constrution)
3) Darul Uloom Tarjuman ul Quran at Rega, Buner PK-78 (construction)
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 8.75 0 0 0 0 8.75 13.25 - 40%
July - 2018
Out of 3 units, all in progress.
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba, Buner PK-79 (construction of students hostel)
2) Jamia Masjid Baro Masjid village Kalpani, Buner PK-78 (constrution)
3) Darul Uloom Tarjuman ul Quran at Rega, Buner PK-78 (construction)
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2020
Tender called on 24/02/2020.
No Image
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2020
Tender called on 24/02/2020.
No Image
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2020
Tender called on 24/02/2020.
No Image
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2020
Tender called on 24/02/2020.
No Image
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2020
Tender called on24/02/2020.
No Image
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 2 0 0 0 0 2 4 - 33%
September - 2018
Completed.
No Image
1) Jamia Masjid Haji Abad, Umarzai PK-129 (improvement/extension)
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 2 0 0 0 0 2 4 - 33%
July - 2018
Finishing in progress.
No Image
1) Jamia Masjid Haji Abad, Umarzai PK-129 (improvement/extension)
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
August - 2019
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
December - 2019
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
November - 2019
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
October - 2019
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
September - 2019
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
May - 2020
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
April - 2020
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
March - 2020
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
February - 2020
Approved.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 17 0 0 0 0 0 0 17 - -
January - 2020
Approved.
No Image
Hangu
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
September - 2018
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah village Teekar Kot Tehsil Barawal, Dir Upper (construction)
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
July - 2018
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah village Teekar Kot Tehsil Barawal, Dir Upper (construction)
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
December - 2019
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
November - 2019
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
October - 2019
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
September - 2019
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
August - 2019
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
May - 2020
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
April - 2020
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
March - 2020
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
February - 2020
Completed and H/O.
No Image
Hangu
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Hangu
30-11--1 30-11--1 - 30-11--1 - 2.002 2 0 0 0 0 2 0.002 - 100%
January - 2020
Completed and H/O.
No Image
Hangu
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 1.216 1.132 0 0 0 0 1.132 0.084 - 93%
September - 2018
Completed.
No Image
1) Masjid Huzaifa, Chokara, Karak (construction of verandah and water reservoir)
45
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 1.216 1.132 0 0 0 0 1.132 0.084 - 93%
July - 2018
Completed.
No Image
1) Masjid Huzaifa, Chokara, Karak (construction of verandah and water reservoir)
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 8.1 0.5 4 4 4 4 4.5 3.6 56% 56%
December - 2019
3 units - 2 complted . 1 work in progress.
No Image
1. Renovation & Improv of United Presbyterian Church
2. Repair & Rehab of Guracwara at Street No. 7 College Town
3. Improv & Renovation of Mandar at Mohallah Sanghir
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 8.1 0.5 4 4 4 4 4.5 3.6 56% 56%
November - 2019
3 units - 2 complted . 1 work in progress.
No Image
1. Renovation & Improv of United Presbyterian Church
2. Repair & Rehab of Guracwara at Street No. 7 College Town
3. Improv & Renovation of Mandar at Mohallah Sanghir
45
(OG)
180491-Renovation & Improvement of Worship Places of Minorities in Khyber Pakhtunkhwa
Kohat
30-11--1 30-11--1 - 30-11--1 - 8.1 0.5 4 4 4 4 4.5 3.6 56% 56%
October - 2019
3 units - 2 complted . 1 work in progress.
No Image
1. Renovation & Improv of United Presbyterian Church
2. Repair & Rehab of Guracwara at Street No. 7 College Town
3. Improv & Renovation of Mandar at Mohallah Sanghir
Pages : 1 2 3