Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, February - 2021, February - 2020, March - 2021, March - 2020, April - 2021, April - 2020, May - 2021, May - 2020, July - 2020, August - 2019, August - 2020, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019, December - 2020,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 6.862 6.862 6.862 6.861 39.51 228.987 15% 15%
December - 2019
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress.
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 15.042 15.042 15.042 6.861 39.51 220.807 18% 15%
November - 2019
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress.
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 15.042 15.042 15.042 6.861 39.51 220.807 18% 15%
October - 2019
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress.
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 15.042 15.042 15.042 6.86 39.509 220.807 18% 15%
September - 2019
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress.
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 0 0 0 0 32.649 235.849 - 12%
August - 2019
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress.
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 61.862 61.862 61.862 16.746 49.395 173.987 35% 18%
May - 2020
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress. Snow Bound
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 61.862 61.862 61.862 16.746 49.395 173.987 35% 18%
April - 2020
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress. Snow Bound
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 61.862 61.862 61.862 16.746 49.395 173.987 35% 18%
March - 2020
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress. Snow Bound
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 61.862 61.862 61.862 16.746 49.395 173.987 35% 18%
February - 2020
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress. Snow Bound
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 268.498 32.649 61.862 61.862 61.862 16.746 49.395 173.987 35% 18%
January - 2020
Multipurpose Hall - BB work in progress. Student Hostel, Lab - Plinth beam in progress. Snow Bound
No Image
1) GGDC Galiyat Abbottabad
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 23 23 23 23 56.426 120.019 32% 32%
December - 2019
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 15 15 15 16.882 50.308 128.019 27% 29%
November - 2019
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 15 15 15 11.254 44.68 128.019 27% 25%
October - 2019
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 15 15 15 0 33.426 128.019 27% 19%
September - 2019
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 0 0 0 0 33.426 143.019 - 19%
August - 2019
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 70 70 70 35.336 68.762 73.019 59% 39%
May - 2020
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 70 70 70 35.336 68.762 73.019 59% 39%
April - 2020
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 70 70 70 35.336 68.762 73.019 59% 39%
March - 2020
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 70 70 70 35.336 68.762 73.019 59% 39%
February - 2020
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Buner
30-11--1 30-11--1 - 30-11--1 - 176.445 33.426 70 70 70 23 56.426 73.019 59% 32%
January - 2020
Academic block - FF in progress. BW in progress.
No Image
1) GGDC Khadu Khel PK-77 Buner
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
December - 2019
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
November - 2019
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
October - 2019
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
September - 2019
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
August - 2019
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 10 10 10 0 277.6 6.325 98% 94%
May - 2020
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
April - 2020
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
March - 2020
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
February - 2020
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Charsadda
30-11--1 30-11--1 - 30-11--1 - 293.925 277.6 0 0 0 0 277.6 16.325 - 94%
January - 2020
Completed & H/O.
No Image
1) GGDC Umarzai PK-57
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12 12 12 1.928 237.772 23.26 91% 88%
December - 2019
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12 12 12 1.928 237.772 23.26 91% 88%
November - 2019
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12 12 12 1.09 236.934 23.26 91% 87%
October - 2019
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12 12 12 0.83 236.674 23.26 91% 87%
September - 2019
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12 12 12 0 235.844 23.26 91% 87%
August - 2019
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12.5 12.5 12.5 4.212 240.056 22.76 92% 89%
May - 2020
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12.5 12.5 12.5 4.212 240.056 22.76 92% 89%
April - 2020
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12.5 12.5 12.5 4.212 240.056 22.76 92% 89%
March - 2020
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 12.5 12.5 12.5 4.212 240.056 22.76 92% 89%
February - 2020
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 271.104 235.844 22 22 22 3.269 239.113 13.26 95% 88%
January - 2020
Finishing in progress.
No Image
1) Establishment of GGDC at Balambat
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 15 14.287 14.287 14.287 123.429 52.124 70% 70%
December - 2019
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 15 14.287 14.287 14.287 123.429 52.124 70% 70%
November - 2019
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 15 15 15 9.307 118.449 52.124 70% 67%
October - 2019
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 15 15 15 9.307 118.449 52.124 70% 67%
September - 2019
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 0 0 0 0 109.142 67.124 - 62%
August - 2019
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 50 50 50 17.466 126.608 17.124 90% 72%
May - 2020
A block completed Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 50 50 50 17.466 126.608 17.124 90% 72%
April - 2020
A block completed Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 50 50 50 17.466 126.608 17.124 90% 72%
March - 2020
A block completed Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 50 50 50 17.466 126.608 17.124 90% 72%
February - 2020
A block completed Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
439
(OG)
100248-Establishment of 15 Govt Colleges in Khyber Pakhtunkhwa for Boys and Girls (Phase-IV)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 176.266 109.142 15 14.287 14.287 14.287 123.429 52.124 70% 70%
January - 2020
Land payment made to land owner. Footing concrete laid.
No Image
GDC Darora PK-91
Pages : 1 2 3