Progressive Review for the month(s) of : January - 2020, January - 2021, February - 2020, February - 2021, March - 2020, March - 2021, April - 2020, April - 2021, May - 2020, May - 2021, July - 2020, August - 2019, August - 2020, September - 2019, September - 2020, October - 2019, October - 2020, November - 2019, December - 2019, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 14.01 481.51 0 100% 100%
December - 2019
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed.
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 6.432 473.932 0 100% 100%
November - 2019
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed.
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 6.432 473.932 0 100% 100%
October - 2019
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed.
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 0 0 467.5 0 100% 100%
September - 2019
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed.
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 0 0 467.5 0 100% 100%
August - 2019
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed.
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109 109 109 34.829 502.329 0 100% 100%
May - 2020
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. Will be complted
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 14.01 481.51 0 100% 100%
April - 2020
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. Will be complted
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 14.01 481.51 0 100% 100%
March - 2020
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. Will be complted
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 14.01 481.51 0 100% 100%
February - 2020
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. Will be complted
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(OG)
140013-F/S and Construction of two Girls Colleges in District Nowshera.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 263.894 467.5 109.394 109.394 27.349 14.01 481.51 0 100% 100%
January - 2020
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. Will be complted
No Image
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
December - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
December - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
October - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
September - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
August - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 0 0 0 0 0 -
July - 2020
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
May - 2021
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
April - 2021
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
March - 2021
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
February - 2021
No Image
436
(New)
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 3450 0 100 100 0 0 0 0 - -
January - 2021
No Image
Pages : 1