Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 14.01 | 481.51 | 0 | 100% |
100% December - 2019 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 6.432 | 473.932 | 0 | 100% |
100% November - 2019 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 6.432 | 473.932 | 0 | 100% |
100% October - 2019 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 0 | 0 | 467.5 | 0 | 100% |
100% September - 2019 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 0 | 0 | 467.5 | 0 | 100% |
100% August - 2019 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress. GGDC Jalozai PK-12 - Completed. |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109 | 109 | 109 | 34.829 | 502.329 | 0 | 100% |
100% May - 2020 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress.
GGDC Jalozai PK-12 - Completed.
Will be complted |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 14.01 | 481.51 | 0 | 100% |
100% April - 2020 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress.
GGDC Jalozai PK-12 - Completed.
Will be complted |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 14.01 | 481.51 | 0 | 100% |
100% March - 2020 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress.
GGDC Jalozai PK-12 - Completed.
Will be complted |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 14.01 | 481.51 | 0 | 100% |
100% February - 2020 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress.
GGDC Jalozai PK-12 - Completed.
Will be complted |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (OG) |
140013-F/S and Construction of two Girls Colleges in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 263.894 | 467.5 | 109.394 | 109.394 | 27.349 | 14.01 | 481.51 | 0 | 100% |
100% January - 2020 |
GGDC Tarkha PK-12 - main building Roof laid, BW in progress.
GGDC Jalozai PK-12 - Completed.
Will be complted |
No Image |
1) GGDC Jalozai PK-12
2) GGDC Tarkha PK-12 | |||||||||||||||||||
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
436 (New) |
200028-Upgradation of 100 High schools to Higher Secondary level (B&G) on need basis in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3450 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
Pages : 1 |