Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2021, February - 2019, February - 2021, March - 2019, March - 2021, April - 2019, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, November - 2018, December - 2018, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Battagram
30-11--1 30-11--1 - 30-11--1 - 53.752 13.336 0 0 0 0 13.336 40.416 - 25%
May - 2021
04- Units 1 Work started 2 Finihsing 3 Roof level 4 Roof liad
No Image
1 GHS Battamori .?.. Rs: 38.475
2 GGMS Huthel .?.. Rs: 11.477 (TS 11.424)
3 GGHS Battagram .?.. Rs: 1.9
4 GHS Battagram No. 2 .?.. Rs: 1.9
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Battagram
30-11--1 30-11--1 - 30-11--1 - 53.752 13.336 0 0 0 0 13.336 40.416 - 25%
April - 2021
03 units - all in progress 1 Work started 2 Finihsing 3 Roof level 4 roof liad
No Image
1 GHS Battamori .?.. Rs: 38.475
2 GGMS Huthel .?.. Rs: 11.477 (TS 11.424)
3 GGHS Battagram .?.. Rs: 1.9
4 GHS Battagram No. 2 .?.. Rs: 1.9
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Battagram
30-11--1 30-11--1 - 30-11--1 - 53.752 13.336 0 0 0 0 13.336 40.416 - 25%
March - 2021
03 units - all in progress 1 Work started 2 Finihsing 3 Roof level 4 roof liad
No Image
1 GHS Battamori .?.. Rs: 38.475
2 GGMS Huthel .?.. Rs: 11.477 (TS 11.424)
3 GGHS Battagram .?.. Rs: 1.9
4 GHS Battagram No. 2 .?.. Rs: 1.9
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Battagram
30-11--1 30-11--1 - 30-11--1 - 53.752 13.336 0 0 0 0 13.336 40.416 - 25%
February - 2021
03 units - all in progress 1 Work started 2 Finihsing 3 Roof level 4 roof liad
No Image
1 GHS Battamori .?.. Rs: 38.475
2 GGMS Huthel .?.. Rs: 11.477 (TS 11.424)
3 GGHS Battagram .?.. Rs: 1.9
4 GHS Battagram No. 2 .?.. Rs: 1.9
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 97.36 13.336 47.465 0 0 0 13.336 36.559 62% 14%
May - 2021
Scheme dropped from ADP 2019-20
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 97.36 13.336 47.465 0 0 0 13.336 36.559 62% 14%
April - 2021
Scheme dropped from ADP 2019-20
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 97.36 13.336 47.465 0 0 0 13.336 36.559 62% 14%
March - 2021
Scheme dropped from ADP 2019-20
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 0 0 0 0 0 32.7 - -
December - 2020
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 0 0 0 0 0 32.7 - -
December - 2020
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 0 0 0 0 0 32.7 - -
October - 2020
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 18.7 0 0 0 0 0 0 18.7 - -
September - 2020
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 18.7 0 0 0 0 0 0 18.7 - -
August - 2020
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 47.465 12.435 12.435 11.027 11.027 0 100% 34%
May - 2021
2- Units -Completed & H/O
No Image
1 GPS Yaqoobabad
2 GPS Zad Khar
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 47.465 12.435 12.435 11.027 11.027 0 100% 34%
April - 2021
2- Units -Completed & H/O
No Image
1 GPS Yaqoobabad
2 GPS Zad Khar
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 47.465 12.435 12.435 11.027 11.027 0 100% 34%
March - 2021
2- Units -Completed & H/O
No Image
1 GPS Yaqoobabad
2 GPS Zad Khar
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 47.465 12.435 12.435 9.988 9.988 0 100% 31%
February - 2021
2- Units -Completed & H/O
No Image
1 GPS Yaqoobabad
2 GPS Zad Khar
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.7 0 47.465 12.435 12.435 9.988 9.988 0 100% 31%
January - 2021
2- Units 1- unit completed. Unit No. MB& Boundary finishing in progress.
No Image
1 GPS Yaqoobabad
2 GPS Zad Khar
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Mansehra
30-11--1 30-11--1 - 30-11--1 - 51.727 0 47.465 1.439 1.439 0 0 4.262 92% -
May - 2021
07- Units 1. Roofing & Dev: Work in progress 2. Roofing & Dev: Work in progress 3. Finishing 4. Plastering 5. Roof Beam Laid 6. Roof Laid 7. S/S in progress
No Image
  1. GMS Nawasher PK 32
  2. GPS Shergarh PK 33
  3. GHS Gandain PK 34
  4. GGHS Bai Bohal PK 32
  5. GHSS Gundain PK 34
  6. GHS Chandor PK 32
  7. GGMS More Bafa
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
December - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
December - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
October - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
September - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
August - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 0 0 0 0 0 - -
July - 2020
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
May - 2021
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
April - 2021
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
March - 2021
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
February - 2021
No Image
424
(OG)
190113-Continuation of Ongoing ADP Schemes for Completion of Balance Work/Liabilities
Provincial
30-11--1 30-11--1 - 30-11--1 - 97 0 47.465 47.465 0 0 0 0 - -
January - 2021
No Image
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 109.805 0 0 0.001 100% -
December - 2018
Site not yet finalized.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 109.805 109.805 109.805 0.001 100% 64%
November - 2018
Approved.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 109.805 109.805 109.805 0.001 100% 64%
November - 2018
Approved.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 0 0 0 0.001 100% -
April - 2019
Site not yet finalized.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 0 0 0 0.001 100% -
March - 2019
Site not yet finalized.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 0 0 0 0.001 100% -
March - 2019
Site not yet finalized.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 0 0 0 0.001 100% -
February - 2019
Site not yet finalized.
No Image
Swabi
424
(OG)
160236-Purchase of Land for Gajju Khan Medical College Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 171.408 0 171.407 171.407 0 0 0 0.001 100% -
January - 2019
Site not yet finalized.
No Image
Swabi
Pages : 1