42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.5 | 6.418 | 0.2 | 0.2 | 0.2 | 0.2 | 6.618 | 4.882 | 58% |
58% September - 2018 |
Out of 4 units, 3 completed, 1 in progress. |
No Image |
1) Jamia Darul Uloom Islamia, Almarkaz-e-Islami, (Berone Huwaid Gate), Bannu City
2) Madrassa Aribia Mazher ul Uloom in Pirat Mama Khel, Bannu
3) Madrassa Zia ul Quran Berone Sukani Gate, Bannu (construction of 3 rooms)
4) Masjid Syed Hussain Shah Kotka Mulagan near Woolen Mill DI.Khan road, Bannu | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.5 | 6.418 | 0 | 0 | 0 | 0 | 6.418 | 5.082 | - |
56% July - 2018 |
Out of 4 units, all in progress. |
No Image |
1) Jamia Darul Uloom Islamia, Almarkaz-e-Islami, (Berone Huwaid Gate), Bannu City
2) Madrassa Aribia Mazher ul Uloom in Pirat Mama Khel, Bannu
3) Madrassa Zia ul Quran Berone Sukani Gate, Bannu (construction of 3 rooms)
4) Masjid Syed Hussain Shah Kotka Mulagan near Woolen Mill DI.Khan road, Bannu | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2.4 | 0.5 | 0.5 | 0.5 | 0 | 2.4 | 0.1 | 97% |
80% September - 2018 |
Roof laid. |
No Image |
Al-Markaz Islamia, Battagram | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2.4 | 0 | 0 | 0 | 0 | 2.4 | 0.6 | - |
80% July - 2018 |
Roof laid. |
No Image |
Al-Markaz Islamia, Battagram | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.5 | 3.272 | 0 | 0 | 0 | 0 | 3.272 | 0.228 | - |
93% September - 2018 |
Completed (2 units). |
No Image |
1) Darul Uloom Faizul Quran Sura Buner PK-77 (construction of class rooms)
2) Darul Uloom Riazul Uloom village Kala Khela Tehsils Daggar (construction of boundary wall, wash rooms and library) | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3.5 | 3.272 | 0 | 0 | 0 | 0 | 3.272 | 0.228 | - |
93% July - 2018 |
Completed (2 units). |
No Image |
1) Darul Uloom Faizul Quran Sura Buner PK-77 (construction of class rooms)
2) Darul Uloom Riazul Uloom village Kala Khela Tehsils Daggar (construction of boundary wall, wash rooms and library) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
13-03-17 | 30-06-18 | - | 14-01-16 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% December - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
13-03-17 | 30-06-18 | - | 14-01-16 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% September - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
13-03-17 | 30-06-18 | - | 14-01-16 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% August - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
13-03-17 | 30-06-18 | - | 14-01-16 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% July - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0 | 1.515 | 0 | 100% |
76% December - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% November - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0 | 1.515 | 0 | 100% |
76% November - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0 | 1.515 | 0 | 100% |
76% November - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% October - 2017 |
Completed. |
No Image |
Sewerage and repair of house at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 3 | 0 | 0 | 0 | 0 | 3 | 5 | - |
38% September - 2018 |
Completed. |
No Image |
1) Mosque at Wazir Abad, Kanro Killi UC Hisara Nehri PK-20 (improvement/construction)
2) Jamia Ahyayul Uloom, Prang PK-17 (construction of students hostel)
3) Sherpao Masjid, Tehsil Tangi PK-21 (rehabilitation/renovation) | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 8 | 3 | 0 | 0 | 0 | 0 | 3 | 5 | - |
38% July - 2018 |
Completed. |
No Image |
1) Mosque at Wazir Abad, Kanro Killi UC Hisara Nehri PK-20 (improvement/construction)
2) Jamia Ahyayul Uloom, Prang PK-17 (construction of students hostel)
3) Sherpao Masjid, Tehsil Tangi PK-21 (rehabilitation/renovation) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% June - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% May - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% April - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.214 | 0.214 | 0.214 | 0.214 | 1.729 | 0.271 | 86% |
86% April - 2019 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% March - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0.214 | 1.729 | 0 | 100% |
86% March - 2019 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0.214 | 1.729 | 0 | 100% |
86% March - 2019 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% February - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0.214 | 1.729 | 0 | 100% |
86% February - 2019 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0 | 0 | 0 | 0 | 1.515 | 0.485 | - |
76% January - 2018 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2 | 1.515 | 0.485 | 0.485 | 0.485 | 0.214 | 1.729 | 0 | 100% |
86% January - 2019 |
Completed & H/O. |
No Image |
Sewerage and repair of House at Christian Colony Shabqadar Charsadda | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
15-12-16 | 30-06-18 | - | 14-01-16 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% December - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
15-12-16 | 30-06-18 | - | 14-01-16 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% September - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
15-12-16 | 30-06-18 | - | 14-01-16 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% August - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
15-12-16 | 30-06-18 | - | 14-01-16 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% July - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% December - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% November - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% November - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% November - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% October - 2017 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% June - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% May - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% April - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% April - 2019 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% March - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% March - 2019 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% March - 2019 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% February - 2018 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% February - 2019 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% January - 2018 |
Completed. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
150167-Improvement and Rehabilitation of Residential Colonies and Warship Places for Minorities in Khyber Pakhtunkhwa (Phase-VI). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3 | 2 | 0 | 0 | 0 | 0 | 2 | 1 | - |
67% January - 2019 |
Completed & H/O. |
No Image |
Paroa Adda DI.Khan (sewerage and repair work of houses at hindu, christian colony) | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6 | 4.596 | 0 | 0 | 0 | 0 | 4.596 | 1.404 | - |
77% September - 2018 |
2 units - 1 completed, 1 plastering in progress. |
No Image |
1) Tafhim ul Quran at Village Munjai Tehsil Balambat, Dir Lower (construction of room)
2) Madrassa Ahya ul Uloom, Dir Lower (construction) | |||||||||||||||||||
42 (OG) |
160093-Improvement and Rehabilitation of Masajids & Darul-Ulooms in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6 | 4.596 | 0 | 0 | 0 | 0 | 4.596 | 1.404 | - |
77% July - 2018 |
2 units - 1 completed, 1 plastering in progress. |
No Image |
1) Tafhim ul Quran at Village Munjai Tehsil Balambat, Dir Lower (construction of room)
2) Madrassa Ahya ul Uloom, Dir Lower (construction) | |||||||||||||||||||