Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 0 | 4.931 | 4.931 | 4.931 | 4.931 | 4.931 | 90.04 | 5% |
5% October - 2020 |
Out of 3 units, all in progress. |
No Image |
1) GGHS Kuthwal PK-48
2) GGHS Bandi Phullan (Pk-46)
3) GGHS Mirpur (Pk-39) | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 0 | 4.931 | 4.931 | 4.931 | 4.931 | 4.931 | 90.04 | 5% |
5% September - 2020 |
Out of 3 units, all in progress. |
No Image |
1) GGHS Kuthwal PK-48
2) GGHS Bandi Phullan (Pk-46)
3) GGHS Mirpur (Pk-39) | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 0 | 0 | 0 | 0 | 0 | 0 | 94.971 | - |
- August - 2020 |
Out of 3 units, all in progress. |
No Image |
1) GGHS Kuthwal PK-48
2) GGHS B | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 0 | 0 | 0 | 0 | 0 | 0 | 94.971 | - |
- July - 2020 |
Out of 3 units, all in progress. |
No Image |
1) GGHS Kuthwal PK-48
2) GGHS B | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 59.061 | 25.614 | 25.614 | 25.614 | 11.016 | 70.077 | 10.296 | 89% |
74% May - 2021 |
03- Units
1. Dev: work in progress, M/B G/F roof laid
2. Completed & H/O
3. Finishing in progress & B/Wall completed |
No Image |
1) GGHS Kuthwal PK-48 .?.?.. TS 29.531
2) GGHS Bandi Phullan (Pk-46) .?.?.. TS 29.005
3) GGHS Mirpur (Pk-39) .?.?.. TS 26.702 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 59.061 | 16.782 | 16.782 | 16.782 | 6.782 | 65.843 | 19.128 | 80% |
69% April - 2021 |
03 units,
1. Dev: work in progress, M/B G/F roof laid
2. Completed & H/O
3. Finishing in progress & B/Wall completed |
No Image |
1) GGHS Kuthwal PK-48 .?.?.. TS 29.531
2) GGHS Bandi Phullan (Pk-46) .?.?.. TS 29.005
3) GGHS Mirpur (Pk-39) .?.?.. TS 26.702 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 59.061 | 6.782 | 6.782 | 6.782 | 6.782 | 65.843 | 29.128 | 69% |
69% March - 2021 |
03 units,
1. Dev: work in progress, M/B G/F roof laid
2. Completed & H/O
3. Finishing in progress & B/Wall completed |
No Image |
1) GGHS Kuthwal PK-48 .?.?.. TS 29.531
2) GGHS Bandi Phullan (Pk-46) .?.?.. TS 29.005
3) GGHS Mirpur (Pk-39) .?.?.. TS 26.702 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 59.061 | 6.782 | 6.782 | 6.782 | 6.782 | 65.843 | 29.128 | 69% |
69% February - 2021 |
03 units,
1. Dev: work in progress, M/B G/F roof laid
2. Completed & H/O
3. Finishing in progress & B/Wall completed |
No Image |
1) GGHS Kuthwal PK-48 .?.?.. TS 29.531
2) GGHS Bandi Phullan (Pk-46) .?.?.. TS 29.005
3) GGHS Mirpur (Pk-39) .?.?.. TS 26.702 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.971 | 59.061 | 6.782 | 6.782 | 6.782 | 6.498 | 65.559 | 29.128 | 69% |
69% January - 2021 |
03 units,
1. Dev: work in progress, M/B G/F roof laid
2. Completed & H/O
3. Finishing in progress & B/Wall completed |
No Image |
1) GGHS Kuthwal PK-48
2) GGHS Bandi Phullan (Pk-46)
3) GGHS Mirpur (Pk-39) | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- December - 2020 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- December - 2020 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- October - 2020 |
Work Order Issued. Site not H/O |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- September - 2020 |
Work Order Issued. Site not H/O |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- August - 2020 |
Work Order Issued. Site not H/O |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 0 | 0 | 0 | 0 | 0 | 43.751 | - |
- July - 2020 |
Work Order Issued. Site not H/O |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 0 | 0 | 0 | 0 | 0 | 43.751 | - |
- May - 2021 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 0 | 0 | 0 | 0 | 0 | 43.751 | - |
- April - 2021 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- March - 2021 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- February - 2021 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.751 | 0 | 7.951 | 7.951 | 7.951 | 0 | 0 | 35.8 | 18% |
- January - 2021 |
Work Order Issued. Site require land purchase |
No Image |
GGHS Bazar Ahmad Khan PK-70 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 8.487 | 8.487 | 8.487 | 8.487 | 8.487 | 17.335 | 33% |
33% December - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 8.487 | 8.487 | 8.487 | 8.487 | 8.487 | 17.335 | 33% |
33% December - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 8.487 | 8.487 | 8.487 | 6.285 | 6.285 | 17.335 | 33% |
24% October - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 8.487 | 8.487 | 8.487 | 6.285 | 6.285 | 17.335 | 33% |
24% September - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 0 | 0 | 0 | 0 | 0 | 25.822 | - |
- August - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 0 | 0 | 0 | 0 | 0 | 25.822 | - |
- July - 2020 |
Work order issued. Site not handed over. |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.822 | 0 | 32.678 | 32.678 | 32.678 | 22.644 | 22.644 | 0 | 100% |
71% May - 2021 |
01-Unit
G/F roof in progress
B/Wall in progress |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.822 | 0 | 32.678 | 32.678 | 32.678 | 22.644 | 22.644 | 0 | 100% |
71% April - 2021 |
G/F roof in progress |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.822 | 0 | 18.476 | 18.476 | 18.476 | 18.476 | 18.476 | 13.346 | 58% |
58% March - 2021 |
G/F roof in progress |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.822 | 0 | 18.476 | 18.476 | 18.476 | 18.476 | 18.476 | 13.346 | 58% |
58% February - 2021 |
G/F roof in progress |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 25.822 | 0 | 18.476 | 18.476 | 18.476 | 15.515 | 15.515 | 7.346 | 72% |
60% January - 2021 |
G/F roof in progress |
No Image |
1) GGHS Matwanai PK-78 | |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 50 | 5.573 | 2276.519 | 131.106 | 95% |
91% December - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2270.946 | 100 | 100 | 50 | 0 | 2270.946 | 180.686 | 93% |
89% November - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2551.632 | 2270.946 | 100 | 100 | 50 | 0 | 2270.946 | 180.686 | 93% |
89% November - 2018 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. Revised DCE submitted. Observations attended. Lies with Finance Deptt for revenue component. Physicallay 90% work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 100 | 8.994 | 2279.94 | 131.106 | 95% |
91% April - 2019 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 50 | 8.932 | 2279.878 | 131.106 | 95% |
91% March - 2019 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 50 | 8.932 | 2279.878 | 131.106 | 95% |
91% March - 2019 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 50 | 8.896 | 2279.842 | 131.106 | 95% |
91% February - 2019 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
60046-Construction of Building for Gomal Medical College, DI.Khan Phase-II. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2502.052 | 2270.946 | 100 | 100 | 50 | 5.573 | 2276.519 | 131.106 | 95% |
91% January - 2019 |
Pack-1 & 2 - completed.
Pack-3 & 4 - in progress. Rectification work completed. |
No Image |
DI.Khan | |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) GGHS Kacha Mali khel Kirri Khaisore (Pk-68)
| |||||||||||||||||||
415 (OG) |
150557-Up-gradation of 50 Govt Girls High Schools to Higher Secondary level (less 25 units). |
DI.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-I/DCE for Rs.17.526 m submitted to DEO F on 29/ |
No Image |
1) GGHS Village Malana PK-66
2) | |||||||||||||||||||
Pages : 1 2 3 |