Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 3.318 | 23.318 | 12.013 | 71% |
56% December - 2019 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 22 M |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 0 | 0 | 0 | 0 | 20 | 22.013 | - |
48% November - 2019 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 22 M |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 0 | 0 | 0 | 0 | 20 | 22.013 | - |
48% October - 2019 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 22 M |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 0 | 0 | 0 | 0 | 20 | 22.013 | - |
48% September - 2019 |
5 Units - Repair nature of work. Work in progress. |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 0 | 0 | 0 | 0 | 20 | 22.013 | - |
48% August - 2019 |
5 Units - Repair nature of work. Work in progress. |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 6.25 | 26.25 | 12.013 | 71% |
62% May - 2020 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 12 M for completion . |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 6.25 | 26.25 | 12.013 | 71% |
62% April - 2020 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 12 M for completion . |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 6.25 | 26.25 | 12.013 | 71% |
62% March - 2020 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 12 M for completion . |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 6.25 | 26.25 | 12.013 | 71% |
62% February - 2020 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 12 M for completion . |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 20 | 10 | 10 | 10 | 6.25 | 26.25 | 12.013 | 71% |
62% January - 2020 |
5 Units - Repair nature of work. Work in progress.
Demand Rs. 12 M for completion . |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% December - 2019 |
Out of 9 units, 8 completed, 1 irreparable |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% November - 2019 |
Out of 9 units, 8 completed, 1 irreparable |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% October - 2019 |
Out of 9 units, 8 completed, 1 irreparable |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% September - 2019 |
Out of 9 units, 8 completed, 1 in progress. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% August - 2019 |
Out of 9 units, 7 completed, 2 in progress. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% May - 2020 |
Out of 9 units, 8 completed, 1 dropped.
Deamnd RS. 1 M as per TS. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% April - 2020 |
Out of 9 units, 8 completed, 1 dropped.
Deamnd RS. 1 M as per TS. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% March - 2020 |
Out of 9 units, 8 completed, 1 dropped.
Deamnd RS. 1 M as per TS. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% February - 2020 |
Out of 9 units, 8 completed, 1 dropped.
Deamnd RS. 1 M as per TS. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% January - 2020 |
Out of 9 units, 8 completed, 1 dropped.
Deamnd RS. 1 M as per TS. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
- | - | - | - | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
- | - | - | - | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
- | - | - | - | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
- | - | - | - | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
No Image | |
368 (New) |
170646-Construction of 100 Students Hostels in Government Higher Secondary School Gagra District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
No Image | |
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% August - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% December - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- December - 2019 |
No Image | |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% November - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% October - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% September - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% May - 2020 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- May - 2020 |
Work in progress. |
No Image |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% April - 2020 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- April - 2020 |
Work in progress. |
No Image |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% March - 2020 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- March - 2020 |
Work in progress. |
No Image |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% February - 2020 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- February - 2020 |
Work in progress. |
No Image |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% January - 2020 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.471 | 0 | 0 | 0 | 0 | 0 | 0 | 168.471 | - |
- January - 2020 |
Work in progress |
No Image |
(reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% December - 2019 |
Completed. Demand for 1.5 required for electrification. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
368 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.509 | 32.014 | 0 | 0 | 0 | 0 | 32.014 | 1.495 | - |
96% November - 2019 |
Completed. |
No Image |
BHU Sonoghore (reconstruction) | |||||||||||||||||||
Pages : 1 2 3 |