Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.286 | 40.826 | 40.826 | 20.413 | 3.704 | 64.99 | 0 | 100% |
65% December - 2018 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.286 | 40.826 | 40.826 | 0 | 0 | 61.286 | 0 | 100% |
61% November - 2018 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.286 | 40.826 | 40.826 | 0 | 0 | 61.286 | 0 | 100% |
61% November - 2018 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.287 | 40.826 | 40.826 | 40.826 | 10.847 | 72.134 | 0 | 100% |
72% April - 2019 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.287 | 40.826 | 40.826 | 40.826 | 6.11 | 67.397 | 0 | 100% |
67% March - 2019 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.287 | 40.826 | 40.826 | 40.826 | 6.11 | 67.397 | 0 | 100% |
67% March - 2019 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.287 | 40.826 | 40.826 | 20.413 | 3.704 | 64.991 | 0 | 100% |
65% February - 2019 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.287 | 40.826 | 40.826 | 20.413 | 3.704 | 64.991 | 0 | 100% |
65% January - 2019 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 10.808 | 391.133 | 0 | 100% |
77% December - 2019 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 8.75 | 389.075 | 0 | 100% |
77% November - 2019 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 8.7 | 389.025 | 0 | 100% |
77% October - 2019 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
160236-Purchase of Land for Gajju Khan Medical College Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 171.408 | 0 | 96.407 | 96.407 | 48.203 | 0 | 0 | 75.001 | 56% |
- September - 2018 |
Approved. |
No Image |
Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 0 | 380.325 | 0 | 100% |
75% September - 2019 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 0 | 380.325 | 0 | 100% |
75% August - 2019 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
160236-Purchase of Land for Gajju Khan Medical College Swabi. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 171.408 | 0 | 96.407 | 96.407 | 0 | 0 | 0 | 75.001 | 56% |
- July - 2018 |
Approved. |
No Image |
Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 127.572 | 60.669 | 440.994 | 0 | 100% |
87% May - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 127.572 | 10.808 | 391.133 | 0 | 100% |
77% April - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 127.572 | 10.808 | 391.133 | 0 | 100% |
77% March - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 127.572 | 10.808 | 391.133 | 0 | 100% |
77% February - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
356 (OG) |
150514-Reconstruction of Old DHQ Hospital, Swabi (Phase-I) |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 507.897 | 380.325 | 127.572 | 127.572 | 31.893 | 10.808 | 391.133 | 0 | 100% |
77% January - 2020 |
GF/FF - A, B, D, E blocks - finishing in progress. 2nd floor - B block Plastering in progress. C block SS in progress.
VRF component - tendering in progress. Revision of sscheme required due to low rates of mechnical works approved in PC-1. |
No Image |
DHQ Hospital Swabi | |||||||||||||||||||
Pages : 1 |