Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
- | - | - | 04-05-17 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- December - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
- | - | - | 04-05-17 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- September - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
- | - | - | 04-05-17 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- August - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
- | - | - | 04-05-17 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- July - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- November - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- October - 2017 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- June - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- May - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- April - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- March - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- February - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 17.51 | 0 | 0 | 0 | 0 | 0 | 0 | 17.51 | - |
- January - 2018 |
Approved. |
No Image |
1) GMS Soukat Abad PK-21
2) GMS Marchaki UC Hisara Nehri PK-18 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
- | - | - | 18-08-15 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 7.787 | 15.224 | 13.963 | 58% |
46% December - 2017 |
SS level. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
- | - | - | 18-08-15 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 4 | 11.437 | 13.963 | 58% |
35% September - 2017 |
DPC level completed. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
- | - | - | 18-08-15 | - | 33 | 7.437 | 0 | 0 | 0 | 0 | 7.437 | 25.563 | - |
23% August - 2017 |
DPC level completed. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
- | - | - | 18-08-15 | - | 33 | 7.437 | 0 | 0 | 0 | 0 | 7.437 | 25.563 | - |
23% July - 2017 |
DPC level completed. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 7.782 | 15.219 | 13.963 | 58% |
46% November - 2017 |
DPC level completed. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 7.782 | 15.219 | 13.963 | 58% |
46% October - 2017 |
DPC level completed. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 8.214 | 8.214 | 8.214 | 7.787 | 15.224 | 17.349 | 47% |
46% June - 2018 |
MB trusses, BW and lavatory in progress. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 8.214 | 8.214 | 8.214 | 7.787 | 15.224 | 17.349 | 47% |
46% May - 2018 |
MB trusses, BW and lavatory in progress. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 8.214 | 8.214 | 8.214 | 7.787 | 15.224 | 17.349 | 47% |
46% April - 2018 |
MB trusses, BW and lavatory in progress. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 7.787 | 7.787 | 7.787 | 7.787 | 15.224 | 17.776 | 46% |
46% March - 2018 |
MB trusses in progress. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 7.787 | 15.224 | 13.963 | 58% |
46% February - 2018 |
SS level. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33 | 7.437 | 11.6 | 11.6 | 11.6 | 7.787 | 15.224 | 13.963 | 58% |
46% January - 2018 |
SS level. |
No Image |
GMS Jinjarit Koh PK-89 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
- | - | - | 18-08-15 | - | 35.37 | 0 | 8 | 8 | 8 | 8 | 8 | 27.37 | 23% |
23% December - 2017 |
Main building, CW - in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
- | - | - | 18-08-15 | - | 35.37 | 0 | 8 | 8 | 8 | 3.922 | 3.922 | 27.37 | 23% |
11% September - 2017 |
BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
- | - | - | 18-08-15 | - | 35.37 | 0 | 0 | 0 | 0 | 0 | 0 | 35.37 | - |
- August - 2017 |
Layout given. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
- | - | - | 18-08-15 | - | 35.37 | 0 | 0 | 0 | 0 | 0 | 0 | 35.37 | - |
- July - 2017 |
Work order issued. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 8 | 8 | 8 | 8 | 8 | 27.37 | 23% |
23% November - 2017 |
Main building - in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 8 | 8 | 8 | 3.922 | 3.922 | 27.37 | 23% |
11% October - 2017 |
Main building - in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 13.342 | 13.342 | 13.342 | 13.342 | 13.342 | 22.028 | 38% |
38% June - 2018 |
GF roof laid. FF/BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 13.342 | 13.342 | 13.342 | 13.342 | 13.342 | 22.028 | 38% |
38% May - 2018 |
GF roof laid. FF/BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 13.342 | 13.342 | 13.342 | 13.342 | 13.342 | 22.028 | 38% |
38% April - 2018 |
GF roof laid. FF/BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 13.432 | 13.432 | 13.432 | 13.342 | 13.342 | 21.938 | 38% |
38% March - 2018 |
GF roof laid. FF/BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 13.432 | 13.432 | 13.432 | 13.342 | 13.342 | 21.938 | 38% |
38% February - 2018 |
GF roof laid. FF/BW in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.37 | 0 | 8 | 8 | 8 | 8 | 8 | 27.37 | 23% |
23% January - 2018 |
GF roof laid. FF in progress. |
No Image |
1) GMS Babagam PK-96 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
02-02-17 | - | - | 04-05-17 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% December - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
02-02-17 | - | - | 04-05-17 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% September - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
02-02-17 | - | - | 04-05-17 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% August - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
02-02-17 | - | - | 04-05-17 | - | 93.2 | 7.024 | 0 | 0 | 0 | 0 | 7.024 | 86.176 | - |
8% July - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% November - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% October - 2017 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Doli Banda PK-39
2) GMS Kamar Dhand PK-39
3) GMS Kamal Khel PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 128.709 | 7.024 | 25.133 | 25.133 | 25.133 | 25.133 | 32.157 | 96.552 | 25% |
25% June - 2018 |
7 units - 1 in progress, 1 work order issued, 1 tender floated, 1 layout given, 2 DCE submitted, 1 non availability of land. |
No Image |
1) GMS Doli Banda PK-39 2) GMs Kammar Dhand PK-39 3) GMs Kamal Khel PK-37 4) GMS Pasta Sanda PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 128.709 | 7.024 | 25.133 | 25.133 | 25.133 | 25.132 | 32.156 | 96.552 | 25% |
25% May - 2018 |
7 units - 1 in progress, 1 work order issued, 1 tender floated, 1 layout given, 2 DCE submitted, 1 non availability of land. |
No Image |
1) GMS Doli Banda PK-39 2) GMs Kammar Dhand PK-39 3) GMs Kamal Khel PK-37 4) GMS Pasta Sanda PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 128.709 | 7.024 | 25.133 | 25.133 | 25.133 | 22.641 | 29.665 | 96.552 | 25% |
23% April - 2018 |
7 units - 1 in progress, 1 work order issued, 1 tender floated, 1 layout given, 2 DCE submitted, 1 non availability of land. |
No Image |
1) GMS Doli Banda PK-39 2) GMs Kammar Dhand PK-39 3) GMs Kamal Khel PK-37 4) GMS Pasta Sanda PK-37 | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.2 | 7.024 | 25.133 | 25.133 | 25.133 | 18.804 | 25.828 | 61.043 | 35% |
28% March - 2018 |
7 units , 2 units work started, 1 AA awaited, 3 DCE submitted, 1 approval under process. |
No Image |
1) GMS Dheri Banda UC Kharmatoo PK-37
2) GMS Chorlaki Shakardara PK-39
3) GMS Doli Banda UC Sudal PK-39
4) GMS Kamar Dhand PK-39
5) GMS Kotani PK-37
6) GMS Kamal Khel PK-37
7) Dheri Banda shiftedto GMS Pasta Sanda | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% February - 2018 |
7 units , 2 units work started, 1 AA Awaited, 3 DCE submitted 1 approval under process. |
ADP's Images |
1) GMS Dheri Banda UC Kharmatoo PK-37
2) GMS Chorlaki Shakardara PK-39
3) GMS Doli Banda UC Sudal PK-39
4) GMS Kamar Dhand PK-39
5) GMS Kotani PK-37
6) GMS Kamal Khel PK-37
7) Dheri Banda shiftedto GMS Pasta Sanda | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.2 | 7.024 | 10 | 10 | 10 | 9.804 | 16.828 | 76.176 | 18% |
18% January - 2018 |
Layout given for S.No3. For remaining units DCE submitted to DEO. |
No Image |
1) GMS Dheri Banda UC Kharmatoo PK-37
2) GMS Chorlaki Shakardara PK-39
3) GMS Doli Banda UC Sudal PK-39
4) GMS Kamar Dhand PK-39
5) GMS Kotani PK-37
6) GMS Kamal Khel PK-37
7) Dheri Banda shiftedto GMS Pasta Sanda | |||||||||||||||||||
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Lakki Marwat |
- | - | - | 18-08-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-I/DCE for Rs.32.503 m sbumitted to DEO F on 25/11/2016. |
No Image |
354 (OG) |
150714-Up-gradation of 20 Govt Boys Middle Schools to High level. |
Lakki Marwat |
- | - | - | 18-08-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.32.503 m sbumitted to DEO F on 25/11/2016. |
No Image |
Pages : 1 2 3 4 |