Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
- | - | - | 28-08-14 | - | 20.6 | 3 | 15 | 15 | 15 | 8.783 | 11.783 | 2.6 | 87% |
57% December - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
- | - | - | 28-08-14 | - | 20.6 | 3 | 15 | 15 | 15 | 2.127 | 5.127 | 2.6 | 87% |
25% September - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
- | - | - | 28-08-14 | - | 20.6 | 3 | 15 | 15 | 15 | 0 | 3 | 2.6 | 87% |
15% August - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
- | - | - | 28-08-14 | - | 20.6 | 3 | 15 | 15 | 15 | 0 | 3 | 2.6 | 87% |
15% July - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 2.127 | 5.127 | 2.6 | 87% |
25% November - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 2.127 | 5.127 | 2.6 | 87% |
25% October - 2017 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 0 | 0 | 0 | 0 | 0 | 0 | 42.013 | - |
- September - 2018 |
Repair nature of work. Work order issued. |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
342 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.013 | 0 | 0 | 0 | 0 | 0 | 0 | 42.013 | - |
- July - 2018 |
Repair nature of work. Tender approval under process. |
No Image |
1) Civil Hospital Sherwan PK-46
2) BHU Ghori PK-46
3) CD Rich Bahen PK-46
4) BHU Langrial PK-47
5) BHU Maira Rumal PK-48
6) BHU Nagri Totial PK-48
7) BHU Phalkot PK-48
8) BHU Seer PK-48
9) BHU Summa Karaks PK-48
10) BHU Bagh Bandi PK-48
11) CD Leeran PK-48 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 15 | 18 | 2.6 | 87% |
87% June - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 12.726 | 15.726 | 2.6 | 87% |
76% May - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 12.726 | 15.726 | 2.6 | 87% |
76% April - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 12.726 | 15.726 | 2.6 | 87% |
76% March - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 10.939 | 13.939 | 2.6 | 87% |
68% February - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GHS Chamhatti PK-46
2) GHSS Bandi Dhundian PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20.6 | 3 | 15 | 15 | 15 | 8.783 | 11.783 | 2.6 | 87% |
57% January - 2018 |
Out of 2 units, 1 plinth beam laid, 1 work order issued but site not H/O. |
No Image |
1) GHS Chamhatti PK-46 2) GHSS Bandi Dhundan PK-46 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
25-10-15 | - | - | 28-08-14 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% December - 2017 |
Out of 2 units, all in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
- | - | - | 28-08-14 | - | 19.264 | 16.267 | 1 | 1 | 1 | 0 | 16.267 | 1.997 | 90% |
84% September - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
- | - | - | 28-08-14 | - | 19.264 | 16.267 | 1 | 1 | 1 | 0 | 16.267 | 1.997 | 90% |
84% August - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
- | - | - | 28-08-14 | - | 19.264 | 16.267 | 0 | 0 | 0 | 0 | 16.267 | 2.997 | - |
84% July - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% November - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 0.218 | 16.485 | 1.997 | 90% |
86% October - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% September - 2018 |
Out of 9 units, 7 completed, 2 in progress. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
342 (OG) |
110007-Reconstruction / Rehabilitation of Health Facilities Damaged in July-August 2010 Floods. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.904 | 10.539 | 0 | 0 | 0 | 0 | 10.539 | 1.365 | - |
89% July - 2018 |
Out of 9 units, 7 completed, 2 in progress. |
No Image |
1) DHO Office Bannu
2) DHO residence Bannu
3) Type-D Hospital Jani Khel
4) CD kalam Tughal Khel
5) CD Zalim Mandan
6) CD Khan Suba Mitha Khel
7) BHU Seru Bada Khel
9) BHU Biland Fatma Khel
9) CD Lawat Landidak (Zamir Gul) | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1.159 | 1.159 | 1.159 | 1.1 | 17.367 | 1.838 | 90% |
90% June - 2018 |
Out of 2 units, 1 completed, 1 in progress. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% May - 2018 |
Out of 2 units, 1 completed, 1 in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% April - 2018 |
Out of 2 units, 1 completed, 1 in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% March - 2018 |
Out of 2 units, 1 completed, 1 in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% February - 2018 |
Out of 2 units, 1 completed, 1 in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72
2) GHS Syed Tughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.264 | 16.267 | 1 | 1 | 1 | 1 | 17.267 | 1.997 | 90% |
90% January - 2018 |
Out of 2 units, all in progress. Demand Rs.2 m. |
No Image |
1) GHS Ghulam Jan Bakka Khel PK-72 2) GHS Syed Toughel Khel PK-73 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
- | - | - | 28-08-14 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-I/DCE under preparation on MRS-2017. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
- | - | - | 28-08-14 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.11.545 m submitted to Director E&S Battagram on 07/04/2016. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
- | - | - | 28-08-14 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.11.545 m submitted to Director E&S Battagram on 07/04/2016. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
- | - | - | 28-08-14 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.11.545 m submitted to Director E&S Battagram on 07/04/2016. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
PC-I/DCE under preparation on MRS-2017. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
PC-I/DCE for Rs.11.545 m submitted to Director E&S Battagram on 07/04/2016. |
No Image |
1) GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
PC-I/DCE for Rs.9.430 m on MRS-2017 submitted to DEO M on 09/04/2018. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
PC-I/DCE for Rs.9.430 m on MRS-2017 submitted to DEO M on 09/04/2018. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
PC-I/DCE for Rs.9.430 m on MRS-2017 submitted to DEO M on 09/04/2018. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
PC-I/DCE on MRS-2017 under preparation. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
PC-I/DCE on MRS-2017 under preparation. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
PC-I/DCE on MRS-2017 under preparation. |
No Image |
GHSS Thakot | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
02-06-15 | - | - | 28-08-14 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 2.902 | 33.432 | 0 | 100% |
91% December - 2017 |
Out of 4 units, 2 completed, 2 in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
02-06-15 | - | - | 28-08-14 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 0.262 | 30.792 | 0 | 100% |
84% September - 2017 |
Out of 4 units, all in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
02-06-15 | - | - | 28-08-14 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 0 | 30.53 | 0 | 100% |
83% August - 2017 |
Out of 4 units, all in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
02-06-15 | - | - | 28-08-14 | - | 36.8 | 30.53 | 0 | 0 | 0 | 0 | 30.53 | 6.27 | - |
83% July - 2017 |
Out of 4 units, all in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 0.262 | 30.792 | 0 | 100% |
84% November - 2017 |
Out of 4 units, 2 completed, 2 in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 0.262 | 30.792 | 0 | 100% |
84% October - 2017 |
Out of 4 units, 2 completed, 2 in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 3.476 | 3.476 | 3.476 | 3.476 | 34.006 | 2.794 | 92% |
92% June - 2018 |
Completed (4 units). |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 2.902 | 33.432 | 0 | 100% |
91% May - 2018 |
Completed (4 units). |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 2.902 | 33.432 | 0 | 100% |
91% April - 2018 |
Completed (4 units). |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||
342 (OG) |
140200-Construction of 100 Examination Halls in High & Higher Secondary Schools. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.8 | 30.53 | 6.27 | 6.27 | 6.27 | 2.902 | 33.432 | 0 | 100% |
91% March - 2018 |
Out of 4 units, 2 completed, 2 in progress. |
No Image |
1) GHS Chinar PK-78
2) GHSS Gadezai PK-79
3) GGHS Nogram PK-77
4) GHS Deewana Baba PK-78 | |||||||||||||||||||