Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
- | 30-06-18 | - | 27-06-14 | - | 11.807 | 6.485 | 3 | 3 | 3 | 1.667 | 8.152 | 2.322 | 80% |
69% December - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
- | 30-06-18 | - | 27-06-14 | - | 11.807 | 6.485 | 3 | 3 | 3 | 1.667 | 8.152 | 2.322 | 80% |
69% September - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
- | 30-06-18 | - | 27-06-14 | - | 11.807 | 6.485 | 3 | 3 | 3 | 0 | 6.485 | 2.322 | 80% |
55% August - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
- | 30-06-18 | - | 27-06-14 | - | 11.807 | 6.485 | 0 | 0 | 0 | 0 | 6.485 | 5.322 | - |
55% July - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 3 | 3 | 3 | 1.667 | 8.152 | 2.322 | 80% |
69% November - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 3 | 3 | 3 | 1.667 | 8.152 | 2.322 | 80% |
69% October - 2017 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 4.319 | 4.319 | 4.319 | 4.319 | 10.804 | 1.003 | 92% |
92% June - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 9.686 | 9.686 | 9.686 | 4.272 | 10.757 | 0 | 100% |
91% May - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 9.686 | 9.686 | 9.686 | 4.272 | 10.757 | 0 | 100% |
91% April - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 4.843 | 4.843 | 4.843 | 3.265 | 9.75 | 0.479 | 96% |
83% March - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 4.843 | 4.843 | 4.843 | 3 | 9.485 | 0.479 | 96% |
80% February - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.807 | 6.485 | 3 | 3 | 3 | 1.667 | 8.152 | 2.322 | 80% |
69% January - 2018 |
Finishing in progress (1 unit). |
No Image |
1) GGPS Akhreela PK-47 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
17-10-14 | 30-06-18 | - | 27-06-14 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 1.2 | 23.288 | 2.962 | 89% |
89% December - 2017 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
17-10-14 | 30-06-18 | - | 27-06-14 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 0 | 22.088 | 2.962 | 89% |
84% September - 2017 |
Out of 3 units, 1 completed, 2 in progress. |
No Image |
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
17-10-14 | 30-06-18 | - | 27-06-14 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 0 | 22.088 | 2.962 | 89% |
84% August - 2017 |
Out of 3 units, 1 completed, 2 in progress. |
No Image |
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
17-10-14 | 30-06-18 | - | 27-06-14 | - | 26.25 | 22.088 | 0 | 0 | 0 | 0 | 22.088 | 4.162 | - |
84% July - 2017 |
Out of 3 units, 1 completed, 2 in progress. |
No Image |
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% December - 2019 |
Foundation in Progress. |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 0.636 | 22.724 | 2.962 | 89% |
87% November - 2017 |
Out of 3 units, 1 completed, 2 in progress. |
No Image |
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% November - 2019 |
Foundation in Progress. |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 0.636 | 22.724 | 2.962 | 89% |
87% October - 2017 |
Out of 3 units, 1 completed, 2 in progress. |
No Image |
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% October - 2019 |
Foundation in Progress. |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% September - 2019 |
Foundation in Progress. |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% August - 2019 |
MB, BW, Tube Well in progress. |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 10.2 | 10.2 | 10.2 | 2.706 | 24.794 | 0 | 100% |
94% June - 2018 |
Completed (3 units). |
No Image |
1) GPS Kotka Ayaz Sarki Khel PK-71
2) GGPS Gul Noor Jan Sardi Khel PK-72
3) GGPS Khadri Muhammad Khel Bahadar Khan PK-72 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 10.2 | 10.2 | 10.2 | 2.706 | 24.794 | 0 | 100% |
94% May - 2018 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
1) GPS Kotka Ayaz Sarki Khel PK-71
2) GGPS Gul Noor Jan Sardi Khel PK-72
3) GGPS Khadri Muhammad Khel Bahadar Khan PK-72 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 20 | 20 | 20 | 0 | 8.75 | 40.587 | 41% |
13% May - 2020 |
Foundation in Progress.
Deamnd Rs. 4 M |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 10.2 | 10.2 | 10.2 | 2.234 | 24.322 | 0 | 100% |
93% April - 2018 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
1) GPS Kotka Ayaz Sarki Khel PK-71
2) GGPS Gul Noor Jan Sardi Khel PK-72
3) GGPS Khadri Muhammad Khel Bahadar Khan PK-72 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% April - 2020 |
Foundation in Progress.
Deamnd Rs. 4 M |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 5.2 | 5.2 | 5.2 | 2.234 | 24.322 | 0 | 100% |
93% March - 2018 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
1) GPS Kotka Ayaz Sarki Khel PK-71
2) GGPS Gul Noor Jan Sardi Khel PK-72
3) GGPS Khadri Muhammad Khel Bahadar Khan PK-72 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% March - 2020 |
Foundation in Progress.
Deamnd Rs. 4 M |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 5.2 | 5.2 | 5.2 | 2.234 | 24.322 | 0 | 100% |
93% February - 2018 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
1) GPS Kotka Ayaz Sarki Khel PK-71
2) GGPS Gul Noor Jan Sardi Khel PK-72
3) GGPS Khadri Muhammad Khel Bahadar Khan PK-72 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% February - 2020 |
Foundation in Progress.
Deamnd Rs. 4 M |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.25 | 22.088 | 1.2 | 1.2 | 1.2 | 1.2 | 23.288 | 2.962 | 89% |
89% January - 2018 |
Out of 3 units, 1 completed, 2 in progress. Demand Rs.4 m. |
No Image |
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 69.337 | 8.75 | 0 | 0 | 0 | 0 | 8.75 | 60.587 | - |
13% January - 2020 |
Foundation in Progress.
Deamnd Rs. 4 M |
No Image |
BHU Kifayat Kot Goraka Nar Dilasa Shah PK-71, Bannu | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
10-03-15 | 30-06-18 | - | 27-06-14 | - | 10.735 | 9.239 | 1.496 | 1.496 | 1.496 | 1.415 | 10.654 | 0 | 100% |
99% December - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
10-03-15 | 30-06-18 | - | 27-06-14 | - | 10.735 | 9.239 | 1.496 | 1.496 | 1.496 | 0 | 9.239 | 0 | 100% |
86% September - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
10-03-15 | 30-06-18 | - | 27-06-14 | - | 10.735 | 9.239 | 1.496 | 1.496 | 1.496 | 0 | 9.239 | 0 | 100% |
86% August - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
10-03-15 | 30-06-18 | - | 27-06-14 | - | 10.735 | 9.239 | 0 | 0 | 0 | 0 | 9.239 | 1.496 | - |
86% July - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% December - 2019 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.735 | 9.239 | 1.496 | 1.496 | 1.496 | 1.415 | 10.654 | 0 | 100% |
99% November - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% November - 2019 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.735 | 9.239 | 1.496 | 1.496 | 1.496 | 1.415 | 10.654 | 0 | 100% |
99% October - 2017 |
Main building - finishing in progress. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% October - 2019 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% September - 2019 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% August - 2019 |
land Paymnet made . Work order issued. Site not yet handed over. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.735 | 9.239 | 1.717 | 1.717 | 1.717 | 1.717 | 10.956 | 0 | 100% |
100% June - 2018 |
Completed & H/O. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.735 | 9.239 | 1.717 | 1.717 | 1.717 | 1.415 | 10.654 | 0 | 100% |
99% May - 2018 |
Completed & H/O. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% May - 2020 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
329 (OG) |
130336-Upgradation of 50 Primary Schools to Middle level in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.735 | 9.239 | 1.717 | 1.717 | 1.717 | 1.415 | 10.654 | 0 | 100% |
99% April - 2018 |
Completed & H/O. |
No Image |
1) GGPS Chalandrai PK-78 | |||||||||||||||||||
329 (OG) |
151066-Estab. of BHU at Koz Shammal UC Battera District Buner and at Shahidan Banda Tehsil Takht Nasrati & BHU at Mandawa UC Latamber, Karak and Kifayat kot Gohar Ka Nar Dillasah Bannu. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.834 | 3.655 | 0 | 0 | 0 | 0 | 3.655 | 55.179 | - |
6% April - 2020 |
Site prparation/Dev: work in progress. |
No Image |
BHU Koz Shamal Battera PK-78 | |||||||||||||||||||
Pages : 1 2 3 4 5 6 |