Progressive Review for the month(s) of : January - 2020, January - 2018, February - 2020, February - 2018, March - 2020, March - 2018, April - 2020, April - 2018, May - 2018, May - 2020, June - 2018, July - 2018, July - 2017, August - 2019, August - 2017, September - 2018, September - 2019, September - 2017, October - 2019, October - 2017, November - 2019, November - 2017, December - 2019, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
- 30-06-18 - 21-01-16 - 80 0 75 75 19.314 0 0 0 - -
December - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
- 30-06-18 - 21-01-16 - 80 0 75 75 19.314 0 0 0 - -
September - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
- 30-06-18 - 21-01-16 - 80 0 75 75 19.314 0 0 0 - -
August - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
- 30-06-18 - 21-01-16 - 80 0 75 75 0 0 0 0 - -
July - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
November - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
October - 2017
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 0 0 0 0 - -
June - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
May - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
April - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
March - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
February - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
January - 2018
PC-I/DCE submitted. Land not handed over.
No Image
321
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 85.298 90.231 90.231 45.115 11.808 97.106 0.001 100% 55%
September - 2018
Block-1 completed, Block-2 dismantling in progress (original scope)
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
321
(OG)
130207-Construction of Two Gyms, Wards and OTs in Paraplegic Centre Hayatabad, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 175.53 85.298 90.231 90.231 0 0 85.298 0.001 100% 49%
July - 2018
Finishing in progress (original scope). Revised approved. Work order issued. Cannot be completed due to enhanced cost/scope.
No Image
Hayatabad Peshawar
Main Building ( 2 Gyms, Wards, Staff Room, Ots, Class rooms) ( original Scope )
Additional Block ( Revised Scope)
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 0.001 0 0 99.999 0 100% 100%
December - 2019
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 0.001 0 0 99.999 0 100% 100%
November - 2019
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 0.001 0 0 99.999 0 100% 100%
October - 2019
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 0.001 0 0 99.999 0 100% 100%
September - 2019
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 0.001 0 0 99.999 0 100% 100%
August - 2019
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 20 20 9.263 109.262 0 100% 100%
May - 2020
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 20 20 6.057 106.056 0 100% 100%
April - 2020
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 20 20 6.057 106.056 0 100% 100%
March - 2020
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 20 20 6.057 106.056 0 100% 100%
February - 2020
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat
321
(OG)
151062-Upgradation of BHU Darmai to RHC in Tehsil Matta, District Swat.
Swat
30-11--1 30-11--1 - 30-11--1 - 100 99.999 0.001 20 20 0 99.999 0 100% 100%
January - 2020
Main building - GF/FF roof laid. Plaster, roof in progress. Ward Block roof laid, floor, joinery in progresss.
No Image
Darmai Swat