Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 0.179 | 1.241 | 0 | 100% |
7% December - 2018 |
Demolition completed. Excavation of dewatering tank in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 0.179 | 1.241 | 0 | 100% |
7% November - 2018 |
Demolition completed. Excavation of dewatering tank in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 0.179 | 1.241 | 0 | 100% |
7% November - 2018 |
Demolition completed. Excavation of dewatering tank in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 16.938 | 3.69 | 4.752 | 0 | 100% |
26% April - 2019 |
Excavation in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 1.4 | 2.462 | 0 | 100% |
14% March - 2019 |
Excavation in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 1.4 | 2.462 | 0 | 100% |
14% March - 2019 |
Excavation in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 1.4 | 2.462 | 0 | 100% |
14% February - 2019 |
Excavation in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
170162-Construction of De-Watering System in Food Grain Godowns in District Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 18 | 1.062 | 16.938 | 16.938 | 8.469 | 1.4 | 2.462 | 0 | 100% |
14% January - 2019 |
Demolition completed. Excavation of dewatering tank in progress. |
No Image |
Nowshera | |||||||||||||||||||
304 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.286 | 0.001 | 0.001 | 0 | 0 | 61.286 | 38.613 | 61% |
61% September - 2018 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
304 (OG) |
150610-Upgradation of BHU Martung to RHC District Shangla. |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.9 | 61.286 | 0.001 | 0.001 | 0 | 0 | 61.286 | 38.613 | 61% |
61% July - 2018 |
Main building - FF roof laid. Category 3, 4 and 5 - in progress. Court Case on additional land acquired. |
No Image |
Shangla | |||||||||||||||||||
Pages : 1 |