297
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 5 0.001 0.001 0 0 5 90.653 5% 5%
September - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.
No Image
297
(OG)
151064-Upgradation of BHU Hazarkhwani to RHC, District Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 95.654 5 0.001 0.001 0 0 5 90.653 5% 5%
July - 2018
Work order issued. Demolition of the existing BHU completed. BW in progress. Modified DCE submitted to client deptt on stanadard drawings.