Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2018, September - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
296
(OG)
151060-Upgradation of BHU Aza Khel to RHC, District Peshawar.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 100 20 25 25 0 0 20 55 45% 20%
September - 2018
Main building - GF - brick masonary competed. FF roof laid of Block-A. Black-B - FF brick mathory in progress.
No Image
Peshawar
296
(OG)
151060-Upgradation of BHU Aza Khel to RHC, District Peshawar.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 100 20 25 25 0 0 20 55 45% 20%
July - 2018
Main building - GF - brick masonary competed. FF roof laid of block-A . Black B- FF Roof under progress.
No Image
Peshawar