Progressive Review for the month(s) of : January - 2019, February - 2019, March - 2019, April - 2019, July - 2020, August - 2020, September - 2020, October - 2020, November - 2018, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
December - 2018
Work order issued to contractor.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
November - 2018
Tender called on 13/09/2018, approval under process.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
November - 2018
Tender called on 13/09/2018, approval under process.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 10 10 10 9.743 9.743 64 14% 13%
April - 2019
SS in progress.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
March - 2019
Work order issued to contractor.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
March - 2019
Work order issued to contractor.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
February - 2019
Work order issued to contractor.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 74 0 0 0 0 0 0 74 - -
January - 2019
Work order issued to contractor.
No Image
Cattle Breeding Diary Farm Harichand, District Charsadda
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 0 0 0 0 0 44.716 - -
December - 2018
Financial bids submitted to CE Center for approval.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 0 0 0 0 0 44.716 - -
November - 2018
Financial bids submitted to CE Center for approval.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 0 0 0 0 0 44.716 - -
November - 2018
Financial bids submitted to CE Center for approval.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 8 8 8 7.959 7.959 36.716 18% 18%
April - 2019
Work in progress. Rs.15 m demanded.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 8 8 8 7.959 7.959 36.716 18% 18%
March - 2019
Work in progress. Rs.15 m demanded.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 8 8 8 7.959 7.959 36.716 18% 18%
March - 2019
Work in progress. Rs.15 m demanded.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 8 8 8 0 0 36.716 18% -
February - 2019
Upto DPC level.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 44.716 0 8 8 8 0 0 36.716 18% -
January - 2019
Upto DPC level.
No Image
Pure Buffaloes Breeding Farm DI.Khan
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 2.5 2.5 2.5 0 0 54.67 4% -
December - 2018
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 0 0 0 0 0 57.17 - -
November - 2018
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 0 0 0 0 0 57.17 - -
November - 2018
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 7 7 7 7 7 50.17 12% 12%
April - 2019
Work in progress.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 7 7 7 7 7 50.17 12% 12%
March - 2019
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 7 7 7 7 7 50.17 12% 12%
March - 2019
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 2.5 2.5 2.5 0 0 54.67 4% -
February - 2019
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 57.17 0 2.5 2.5 2.5 0 0 54.67 4% -
January - 2019
Work order issued.
No Image
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi)
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
December - 2018
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
November - 2018
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
November - 2018
No Image
29
(OG)
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program).
Provincial
30-11--1 30-11--1 - 30-11--1 - 643.614 92.11 0 0 0 0 92.11 0 - -
October - 2020
No Image
29
(OG)
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program).
Provincial
30-11--1 30-11--1 - 30-11--1 - 643.614 92.11 0 0 0 0 92.11 0 - -
September - 2020
No Image
29
(OG)
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program).
Provincial
30-11--1 30-11--1 - 30-11--1 - 643.614 92.11 0 0 0 0 92.11 0 - -
August - 2020
No Image
29
(OG)
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program).
Provincial
30-11--1 30-11--1 - 30-11--1 - 643.614 92.11 0 0 0 0 92.11 0 -
July - 2020
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
April - 2019
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
March - 2019
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
March - 2019
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
February - 2019
No Image
29
(OG)
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 276.6 0 50 50 0 0 0 0 - -
January - 2019
No Image