Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- December - 2018 |
Work order issued to contractor. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- November - 2018 |
Tender called on 13/09/2018, approval under process. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- November - 2018 |
Tender called on 13/09/2018, approval under process. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 10 | 10 | 10 | 9.743 | 9.743 | 64 | 14% |
13% April - 2019 |
SS in progress. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- March - 2019 |
Work order issued to contractor. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- March - 2019 |
Work order issued to contractor. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- February - 2019 |
Work order issued to contractor. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74 | 0 | 0 | 0 | 0 | 0 | 0 | 74 | - |
- January - 2019 |
Work order issued to contractor. |
No Image |
Cattle Breeding Diary Farm Harichand, District Charsadda | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 0 | 0 | 0 | 0 | 0 | 44.716 | - |
- December - 2018 |
Financial bids submitted to CE Center for approval. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 0 | 0 | 0 | 0 | 0 | 44.716 | - |
- November - 2018 |
Financial bids submitted to CE Center for approval. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 0 | 0 | 0 | 0 | 0 | 44.716 | - |
- November - 2018 |
Financial bids submitted to CE Center for approval. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 8 | 8 | 8 | 7.959 | 7.959 | 36.716 | 18% |
18% April - 2019 |
Work in progress. Rs.15 m demanded. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 8 | 8 | 8 | 7.959 | 7.959 | 36.716 | 18% |
18% March - 2019 |
Work in progress. Rs.15 m demanded. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 8 | 8 | 8 | 7.959 | 7.959 | 36.716 | 18% |
18% March - 2019 |
Work in progress. Rs.15 m demanded. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 8 | 8 | 8 | 0 | 0 | 36.716 | 18% |
- February - 2019 |
Upto DPC level. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 44.716 | 0 | 8 | 8 | 8 | 0 | 0 | 36.716 | 18% |
- January - 2019 |
Upto DPC level. |
No Image |
Pure Buffaloes Breeding Farm DI.Khan | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 2.5 | 2.5 | 2.5 | 0 | 0 | 54.67 | 4% |
- December - 2018 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 0 | 0 | 0 | 0 | 0 | 57.17 | - |
- November - 2018 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 0 | 0 | 0 | 0 | 0 | 57.17 | - |
- November - 2018 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 7 | 7 | 7 | 7 | 7 | 50.17 | 12% |
12% April - 2019 |
Work in progress. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 7 | 7 | 7 | 7 | 7 | 50.17 | 12% |
12% March - 2019 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 7 | 7 | 7 | 7 | 7 | 50.17 | 12% |
12% March - 2019 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 2.5 | 2.5 | 2.5 | 0 | 0 | 54.67 | 4% |
- February - 2019 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.17 | 0 | 2.5 | 2.5 | 2.5 | 0 | 0 | 54.67 | 4% |
- January - 2019 |
Work order issued. |
No Image |
1) Livestock experiment station Jabba (non-residential building)
2) Livestock experiment station Jabba (residential building)
3) Summer Camp Office Naran (Batakundi) | |||||||||||||||||||
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
No Image | |
29 (OG) |
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 643.614 | 92.11 | 0 | 0 | 0 | 0 | 92.11 | 0 | - |
- October - 2020 |
No Image | |
29 (OG) |
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 643.614 | 92.11 | 0 | 0 | 0 | 0 | 92.11 | 0 | - |
- September - 2020 |
No Image | |
29 (OG) |
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 643.614 | 92.11 | 0 | 0 | 0 | 0 | 92.11 | 0 | - |
- August - 2020 |
No Image | |
29 (OG) |
190105-Poverty Alleviation through Development of Rural Poultry in Khyber Pakhtunkhwa (Provincial Share-PM's Agriculture Emergency Program). |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 643.614 | 92.11 | 0 | 0 | 0 | 0 | 92.11 | 0 | - |
July - 2020 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
No Image | |
29 (OG) |
170086-Improvement of Existing Livestock Breeding Farms in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 276.6 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
No Image | |
Pages : 1 |