Progressive Review for the month(s) of : January - 2020, February - 2020, March - 2020, April - 2020, May - 2020, August - 2019, September - 2019, October - 2019, November - 2019, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 30 7.5 0 30 72.571 45% 23%
December - 2019
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 30 7.5 0 30 72.571 45% 23%
November - 2019
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 30 7.5 0 30 72.571 45% 23%
October - 2019
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 30 0 0 30 72.571 45% 23%
September - 2019
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 30 0 0 30 72.571 45% 23%
August - 2019
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 24.5 2 0.115 30.115 72.571 45% 23%
May - 2020
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 24.5 2 0.115 30.115 72.571 45% 23%
April - 2020
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 24.5 2 0.115 30.115 72.571 45% 23%
March - 2020
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 24.5 2 0.115 30.115 72.571 45% 23%
February - 2020
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
281
(OG)
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank.
Tank
30-11--1 30-11--1 - 30-11--1 - 132.571 30 30 24.5 2 0.016 30.016 72.571 45% 23%
January - 2020
MB - foundation in progress. Offices - finishing in progress. BW 80% work completed.
No Image
Tank
Pages : 1