Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 30 | 7.5 | 0 | 30 | 72.571 | 45% |
23% December - 2019 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 30 | 7.5 | 0 | 30 | 72.571 | 45% |
23% November - 2019 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 30 | 7.5 | 0 | 30 | 72.571 | 45% |
23% October - 2019 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 30 | 0 | 0 | 30 | 72.571 | 45% |
23% September - 2019 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 30 | 0 | 0 | 30 | 72.571 | 45% |
23% August - 2019 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 24.5 | 2 | 0.115 | 30.115 | 72.571 | 45% |
23% May - 2020 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 24.5 | 2 | 0.115 | 30.115 | 72.571 | 45% |
23% April - 2020 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 24.5 | 2 | 0.115 | 30.115 | 72.571 | 45% |
23% March - 2020 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 24.5 | 2 | 0.115 | 30.115 | 72.571 | 45% |
23% February - 2020 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||
281 (OG) |
170606-Construction of Food Grain Godowns of 3000 Ton Capacity in District Tank. |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 132.571 | 30 | 30 | 24.5 | 2 | 0.016 | 30.016 | 72.571 | 45% |
23% January - 2020 |
MB - foundation in progress.
Offices - finishing in progress.
BW 80% work completed. |
No Image |
Tank | |||||||||||||||||||