Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% December - 2019 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% November - 2019 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% October - 2019 |
Civil - Completed.
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% September - 2019 |
Civil - Completed.
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% August - 2019 |
Civil - Completed.
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% May - 2020 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% April - 2020 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% March - 2020 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% February - 2020 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% January - 2020 |
Completed & H/O
Demand bill for meter paid to WAPDA, but not yet installed / energized. |
No Image |
DI.Khan | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 5 | 5 | 5 | 5 | 17 | 80.69 | 17% |
17% December - 2019 |
Lean concrete in foundation laid. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 5 | 5 | 5 | 5 | 17 | 80.69 | 17% |
17% November - 2019 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 5 | 5 | 5 | 5 | 17 | 80.69 | 17% |
17% October - 2019 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 0 | 0 | 0 | 0 | 12 | 85.69 | - |
12% September - 2019 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 0 | 0 | 0 | 0 | 12 | 85.69 | - |
12% August - 2019 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 20 | 20 | 20 | 20 | 32 | 65.69 | 33% |
33% May - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 20 | 20 | 20 | 20 | 32 | 65.69 | 33% |
33% April - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 20 | 20 | 20 | 20 | 32 | 65.69 | 33% |
33% March - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 20 | 20 | 20 | 20 | 32 | 65.69 | 33% |
33% February - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 5 | 5 | 5 | 5 | 17 | 80.69 | 17% |
17% January - 2020 |
Lean concrete in foundation laid. Demand Rs. 50 M |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 5 | 5 | 5 | 5 | 130.887 | 91.363 | 59% |
59% December - 2019 |
GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity & Sanatory work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 10 | 10 | 10 | 1.69 | 127.577 | 86.363 | 61% |
57% November - 2019 |
GF, FF tile completed. Plastering, Plumbing, Doors in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 10 | 10 | 10 | 0 | 125.887 | 86.363 | 61% |
57% October - 2019 |
GF, FF tile completed. Plastering, Plumbing, Doors in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 0 | 0 | 0 | 0 | 125.887 | 96.363 | - |
57% September - 2019 |
GF, FF tile completed. Plastering, Plumbing, Doors in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 0 | 0 | 0 | 0 | 125.887 | 96.363 | - |
57% August - 2019 |
GF, FF tile completed. Plastering, Plumbing, Doors in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 20 | 20 | 20 | 20 | 145.887 | 76.363 | 66% |
66% May - 2020 |
B/W & Brick work completed GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity, Sanatory & Fiber Glass work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 20 | 20 | 20 | 11.066 | 136.953 | 76.363 | 66% |
62% April - 2020 |
B/W & Brick work completed GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity, Sanatory & Fiber Glass work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 20 | 20 | 20 | 11.066 | 136.953 | 76.363 | 66% |
62% March - 2020 |
B/W & Brick work completed GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity, Sanatory & Fiber Glass work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 20 | 20 | 20 | 11.066 | 136.953 | 76.363 | 66% |
62% February - 2020 |
B/W & Brick work completed GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity, Sanatory & Fiber Glass work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 125.887 | 20 | 20 | 20 | 8.481 | 134.368 | 76.363 | 66% |
60% January - 2020 |
GF, FF tile completed. Plastering, Plumbing,Doors work completed. Electricity & Sanatory work in progress.
Demand Rs. 30 M |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- December - 2019 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- November - 2019 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- October - 2019 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- September - 2019 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- August - 2019 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- May - 2020 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- April - 2020 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- March - 2020 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- February - 2020 |
No Image | |
270 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 407 | 265 | 40 | 40 | 0 | 0 | 265 | 0 | - |
- January - 2020 |
No Image | |
270 (OG) |
170262-Construction of Food Grain Godowns of 2000 Ton Capacity in District Torghar. |
Tor Ghar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 111.517 | 0.05 | 9.996 | 9.996 | 4.998 | 0 | 0.05 | 101.471 | 9% |
0% September - 2018 |
Work order issued. UET Peshawar has been requesed for design. |
No Image |
Tor Ghar | |||||||||||||||||||
270 (OG) |
170262-Construction of Food Grain Godowns of 2000 Ton Capacity in District Torghar. |
Tor Ghar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 111.517 | 0.05 | 9.996 | 9.996 | 0 | 0 | 0.05 | 101.471 | 9% |
0% July - 2018 |
Work order issued. UET Peshawar has been requesed for design. |
No Image |
Tor Ghar | |||||||||||||||||||
Pages : 1 |