267
(OG)
170617-Construction of Food Grain Godowns of 2000 Ton Capacity in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 94.8 0 0.001 0.001 0 0 0 94.799 0% -
September - 2018
Work order issued. Land not handed over.
No Image
Kohistan
267
(OG)
170617-Construction of Food Grain Godowns of 2000 Ton Capacity in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 94.8 0 0.001 0.001 0 0 0 94.799 0% -
July - 2018
Work order issued. Land not handed over.
No Image
Kohistan