Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2018, September - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
259
(OG)
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 127.117 7.5 20 20 10 10 17.5 99.617 22% 14%
September - 2018
Raft foundation completed. Columns in progress.
No Image
Construction of Food Grain Godown at Nar Hafiz Abad PK-71
259
(OG)
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 127.117 7.5 20 20 0 0 7.5 99.617 22% 6%
July - 2018
Foundation of RCC in progress.
No Image
Construction of Food Grain Godown at Nar Hafiz Abad PK-71
Pages : 1