Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- December - 2020 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- December - 2020 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- May - 2021 |
01-Unit
Work order issued |
No Image |
01 Nos In Dist: Bannu | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- April - 2021 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- March - 2021 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- February - 2021 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.981 | 0 | 0 | 0 | 0 | 0 | 0 | 99.981 | - |
- January - 2021 |
Procurement in progress |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 10 | 10 | 10 | 10 | 10 | 89.715 | 10% |
10% December - 2020 |
work completed upto plinth level. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 10 | 10 | 10 | 10 | 10 | 89.715 | 10% |
10% December - 2020 |
work completed upto plinth level. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 0 | 0 | 0 | 0 | 0 | 99.715 | - |
- October - 2020 |
Foundation in progress. Funds to the tune of Rs 10.000 (M) is required dated 27/08/2020. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 0 | 0 | 0 | 0 | 0 | 99.715 | - |
- September - 2020 |
Funds to the tune of Rs 10.000 (M) is required dated 27/08/2020. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 0 | 0 | 0 | 0 | 0 | 99.715 | - |
- August - 2020 |
Funds to the tune of Rs 10.000 (M) is required dtt?27/08/2020 |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 0 | 0 | 0 | 0 | 0 | 99.715 | - |
- July - 2020 |
Approved. Procuremnet in progress. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 11 | 11 | 11 | 11 | 11 | 88.715 | 11% |
11% May - 2021 |
01- Unit
Building upto lintel level
Demand Rs: 30 M |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 11 | 11 | 11 | 11 | 11 | 88.715 | 11% |
11% April - 2021 |
Building upto lintel level
Demand Rs: 30 M |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 11 | 11 | 11 | 11 | 11 | 88.715 | 11% |
11% March - 2021 |
Building upto lintel level |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 11 | 11 | 11 | 11 | 11 | 88.715 | 11% |
11% February - 2021 |
Building upto lintel level |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.715 | 0 | 10 | 10 | 10 | 10 | 10 | 89.715 | 10% |
10% January - 2021 |
work completed upto plinth level. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 0 | 0 | 0 | 0 | 0 | 99.175 | - |
- December - 2020 |
Excavtion in progress.
Demand Rs. 40 M
TS under preparation |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 0 | 0 | 0 | 0 | 0 | 99.175 | - |
- December - 2020 |
Excavtion in progress.
Demand Rs. 40 M
TS under preparation |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 20 | 20 | 20 | 5 | 5 | 79.175 | 20% |
5% May - 2021 |
Female indoor Gymansium & offices = G/F Col: in progress |
No Image |
Gymnasium for Female and Multi Purpose Hall Kohat | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 5 | 5 | 5 | 5 | 5 | 94.175 | 5% |
5% April - 2021 |
G/F column in progress |
No Image |
Gymnasium for Female and Multi Purpose Hall Kohat | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 5 | 5 | 5 | 5 | 5 | 94.175 | 5% |
5% March - 2021 |
G/F column in progress |
No Image |
Gymnasium for Female and Multi Purpose Hall Kohat | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 5 | 5 | 5 | 5 | 5 | 94.175 | 5% |
5% February - 2021 |
G/F column in progress |
No Image |
Gymnasium for Female and Multi Purpose Hall Kohat | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.175 | 0 | 0 | 0 | 0 | 0 | 0 | 99.175 | - |
- January - 2021 |
Excavtion in progress.
Demand Rs. 40 M
TS under preparation |
No Image |
Gymnasium for Female and Multi Purpose Hall Kohat | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 15 | 15 | 15 | 7.989 | 53.112 | 22.848 | 72% |
64% December - 2020 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 15 | 15 | 15 | 7.989 | 53.112 | 22.848 | 72% |
64% December - 2020 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 0 | 15 | 15 | 15 | 4.958 | 4.958 | 67.971 | 18% |
6% October - 2020 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 0 | 15 | 15 | 15 | 4.958 | 4.958 | 67.971 | 18% |
6% September - 2020 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 0 | 0 | 0 | 0 | 0 | 0 | 82.971 | - |
- August - 2020 |
Super structure in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 0 | 0 | 0 | 0 | 0 | 0 | 82.971 | - |
- July - 2020 |
Super structure in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 19 | 19 | 19 | 19 | 64.123 | 18.848 | 77% |
77% May - 2021 |
01- Unit
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 19 | 19 | 19 | 19 | 64.123 | 18.848 | 77% |
77% April - 2021 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 19 | 19 | 19 | 13.584 | 58.707 | 18.848 | 77% |
71% March - 2021 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 19 | 19 | 19 | 13.584 | 58.707 | 18.848 | 77% |
71% February - 2021 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.971 | 45.123 | 19 | 19 | 19 | 12.309 | 57.432 | 18.848 | 77% |
69% January - 2021 |
Roofing in progress. |
No Image |
Construction of Gymnasium for female at Marda | |||||||||||||||||||
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% December - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% December - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% October - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% September - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% August - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 0 | 0 | 0 | 40 | 585 | 16% |
6% July - 2020 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% May - 2021 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% April - 2021 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% March - 2021 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% February - 2021 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700 | 40 | 75 | 75 | 0 | 0 | 40 | 585 | 16% |
6% January - 2021 |
Approved. |
No Image |
2027 (OG) |
180561-F/S and Establishment of Female indoor sports facilities at divisional headquarters in Khyber Pakhtunkhwa |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99 | 0 | 0 | 0 | 0 | 0 | 0 | 99 | - |
- October - 2020 |
Approved. |
No Image |
Pages : 1 2 |