Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 5

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
October - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
September - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
August - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
May - 2021
04- Units 1. Work started 2. Work order issued 3. Work started 4. Work order issued
No Image
1  Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
April - 2021
Approved.
No Image
1  Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
March - 2021
Approved.
No Image
1  Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
February - 2021
Approved.
No Image
1  Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 35.532 0 0 0 0 0 0 35.532 - -
January - 2021
Approved.
No Image
1  Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
October - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
September - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
August - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
May - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
April - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
March - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
February - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Bannu
30-11--1 30-11--1 - 30-11--1 - 35.02 0 0 0 0 0 0 35.02 - -
January - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
December - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
October - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
September - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
August - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 3.2 3.2 3.2 2.3 2.3 38.66 8% 5%
May - 2021
05- Units 1. Layout given 2. Volley Ball court in progress 3. Levelling Dressing in progress 4. Badmenton, Basket Ball, Cricket Pitch & Volley Ball court in progress 5. Levelling Dressing in progress/Layout given for pitches
No Image
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 3.2 3.2 3.2 2.3 2.3 38.66 8% 5%
April - 2021
05 units work in porgress Funds Demanded rs: 20 M
No Image
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 3.2 3.2 3.2 2.3 2.3 38.66 8% 5%
March - 2021
05 units work in porgress Funds Demanded rs: 20 M
No Image
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 3.2 3.2 3.2 2.3 2.3 38.66 8% 5%
February - 2021
05 units work in porgress Funds Demanded rs: 20 M
No Image
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Buner
30-11--1 30-11--1 - 30-11--1 - 41.86 0 0 0 0 0 0 41.86 - -
January - 2021
05 units work in porgress Funds Demanded rs: 20 M
No Image
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
October - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
September - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
August - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
May - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
April - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
March - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
February - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.01 0 0 0 0 0 0 36.01 - -
January - 2021
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 14.77 14.77 14.77 6.562 6.562 0 100% 58%
December - 2020
work in progress.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 14.77 14.77 14.77 6.562 6.562 0 100% 58%
December - 2020
work in progress.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 10.93 10.93 10.93 0 0 0.41 96% -
October - 2020
work in progress.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 10.93 10.93 10.93 0 0 0.41 96% -
September - 2020
work in progress.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 0 0 0 0 0 11.34 - -
August - 2020
Approved.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 22.938 22.938 22.938 13.848 13.848 0 100% 100%
May - 2021
work in progress.
No Image
  1. PG at GHS Ayun
  2. PG at GHS Sweer
 
Scope of work:
  • Stairs
  • Leveling
  • Dressing
  • Stage
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 22.938 22.938 22.938 13.848 13.848 0 100% 100%
April - 2021
work in progress.
No Image
  1. PG at GHS Ayun
  2. PG at GHS Sweer
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 14.77 14.77 14.77 10.493 10.493 0 100% 93%
March - 2021
work in progress.
No Image
  1. PG at GHS Ayun
  2. PG at GHS Sweer
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 0 0 0 0 0 11.34 - -
February - 2021
work in progress.
No Image
  1. PG at GHS Ayun
  2. PG at GHS Sweer
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 11.34 0 14.77 14.77 14.77 10.493 10.493 0 100% 93%
January - 2021
work in progress.
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 33.43 0 16.209 16.209 16.209 9.867 9.867 17.221 48% 30%
December - 2020
Approved. Work is in progress Rs.24.440 M IS REQUIRED DURING NEXT FININCIAL YEAR 2020-21
No Image
2024
(OG)
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn).
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 33.43 0 16.209 16.209 16.209 9.867 9.867 17.221 48% 30%
December - 2020
Approved. Work is in progress Rs.24.440 M IS REQUIRED DURING NEXT FININCIAL YEAR 2020-21
No Image