Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 11.896 | 5.948 | 5.948 | 53.998 | 0 | 100% |
97% October - 2020 |
Flooring in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 11.896 | 5.948 | 0 | 48.05 | 0 | 100% |
86% September - 2020 |
Finishing in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 11.896 | 0 | 0 | 48.05 | 0 | 100% |
86% August - 2020 |
FF roof laid. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 0 | 0 | 0 | 48.05 | 0 | 100% |
86% July - 2020 |
FF roof laid. |
No Image |
Special Education Complex Chakdara Dir Lower< | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 0 | 11.896 | 8.918 | 8.918 | 8.882 | 0 | 0 |
May - 2021 |
Flooring in progress. |
No Image | |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 8.918 | 8.918 | 5.215 | 53.265 | 0 | 100% |
95% April - 2021 |
Flooring in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 8.918 | 8.918 | 5.215 | 53.265 | 0 | 100% |
95% March - 2021 |
Flooring in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 8.918 | 8.918 | 5.215 | 53.265 | 0 | 100% |
95% February - 2021 |
Flooring in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
1958 (OG) |
160407-Construction of Special Education Complex Chakdara Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.9 | 48.05 | 11.896 | 8.918 | 8.918 | 5.215 | 53.265 | 0 | 100% |
95% January - 2021 |
Flooring in progress. |
No Image |
Special Education Complex Chakdara Dir Lower | |||||||||||||||||||
Pages : 1 |