Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 25 | 0 | 0 | 32.384 | 32.418 | 64% |
36% October - 2020 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress. |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 25 | 0 | 0 | 32.384 | 32.418 | 64% |
36% September - 2020 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress. |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 25 | 0 | 0 | 32.384 | 32.418 | 64% |
36% August - 2020 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress. |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 0 | 0 | 0 | 32.384 | 32.418 | 64% |
36% July - 2020 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 25 | 25 | 16.864 | 49.248 | 32.418 | 64% |
55% May - 2021 |
01- Unit
Block A+B+C+D+E+F plastering.
FF Plastering & B/W in progress.
TS under Prep |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 12.5 | 12.5 | 8.76 | 41.144 | 32.418 | 64% |
46% April - 2021 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress.
TS under Prep |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 12.5 | 12.5 | 8.76 | 41.144 | 32.418 | 64% |
46% March - 2021 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress.
TS under Prep |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 12.5 | 12.5 | 8.76 | 41.144 | 32.418 | 64% |
46% February - 2021 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress.
TS under Prep |
No Image |
Nowshera | |||||||||||||||||||
1956 (OG) |
160403-Construction of Social Welfare Complex at Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 89.802 | 32.384 | 25 | 0 | 0 | 0 | 32.384 | 32.418 | 64% |
36% January - 2021 |
1) Block A+B+C+D+E+F plastering.
2. FF Plastering & B/W in progress.
TS under Prep |
No Image |
Nowshera | |||||||||||||||||||
Pages : 1 |