1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-I/DCE submitted to SE north dated 15/9/2020. |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-I/DCE submitted to SE north dated 15/9/2020. |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-I/DCE submitted to SE north dated 15/9/2020. |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-1 amounting to Rs 448.98 (M) re-submitted to P&D on 07 Oct 2020. Deferred in Pre-PDWP meeting held on 19.10.2020 with observation that design of the said road may be vetted by the consultant. Submitted to M/S NESPAK on 15/10/2020 . Survey Started by NESPAK team |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
PC-1 amounting to Rs 448.98 (M) re-submitted to P&D on 07 Oct 2020. Deferred in Pre-PDWP meeting held on 19.10.2020 with observation that design of the said road may be vetted by the consultant. Submitted to M/S NESPAK on 15/10/2020 . Survey Started by NESPAK team |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
PC-1 amounting to Rs 448.98 (M) re-submitted to P&D on 07 Oct 2020. Deferred in Pre-PDWP meeting held on 19.10.2020 with observation that design of the said road may be vetted by the consultant. Submitted to M/S NESPAK on 15/10/2020 . Survey Started by NESPAK team |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
PC-1 amounting to Rs 448.98 (M) re-submitted to P&D on 07 Oct 2020. Deferred in Pre-PDWP meeting held on 19.10.2020 with observation that design of the said road may be vetted by the consultant. Submitted to M/S NESPAK on 15/10/2020 . Survey Started by NESPAK team |
No Image |
1946 (New) |
195293-Improvement and Rehabilitation of Frontier Road from Matani to Takhtabaig (28 Km) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 449.37 | 0 | 50 | 50 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
PC-1 amounting to Rs 448.98 (M) re-submitted to P&D on 07 Oct 2020. Deferred in Pre-PDWP meeting held on 19.10.2020 with observation that design of the said road may be vetted by the consultant. Submitted to M/S NESPAK on 15/10/2020 . Survey Started by NESPAK team |
No Image |