Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 20.304 20.304 10.278 10.278 76.545 28% 10%
May - 2021
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 20.304 20.304 5.228 5.228 76.545 28% 5%
April - 2021
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 30 10 4.851 4.851 76.545 28% 5%
December - 2020
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 30 10 4.851 4.851 76.545 28% 5%
December - 2020
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 30 10 0 0 76.545 28% -
October - 2020
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 30 10 0 0 76.545 28% -
September - 2020
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 30 0 0 0 76.545 28% -
August - 2020
Work order issued.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 0 0 0 0 0 -
July - 2020
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 20.304 20.304 5.228 5.228 76.545 28% 5%
March - 2021
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 20.304 20.304 5.228 5.228 76.545 28% 5%
February - 2021
Work started.
No Image
1939
(OG)
195277-Improvement and widening of black topped road from Ali Khel to Nokori upto NWA Border Sub Division Wazir Bannu ( 5km) (ER) (AIP)
FR Bannu
30-11--1 30-11--1 - 30-11--1 - 106.545 0 30 20.304 20.304 5.228 5.228 76.545 28% 5%
January - 2021
Work started.
No Image