Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 35.678 35.678 0 0 128.896 44% -
May - 2021
Length 10 Km - EW Started
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 35.678 35.678 0 0 128.896 44% -
April - 2021
Length 10 Km - EW Started
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 35.678 0 0 128.896 44% -
December - 2020
Re-Tendering under process.
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 35.678 0 0 128.896 44% -
December - 2020
Re-Tendering under process.
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 20 0 0 128.896 44% -
October - 2020
Re-Tendering under process.
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 0 0 0 128.896 44% -
September - 2020
Re-Tendering under process.
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 0 0 0 128.896 44% -
August - 2020
Tendering under process.
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 0 0 0 0 0 -
July - 2020
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 35.678 35.678 0 0 128.896 44% -
March - 2021
work in progress
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 35.678 35.678 0 0 128.896 44% -
February - 2021
work in progress
No Image
1936
(OG)
195278-Improvement & Widening of Road Main Khoi Bahara Road Zardad Koroona (10-KMs) (ER) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 228.896 0 100 100 35.678 0 0 128.896 44% -
January - 2021
Re-Tendering under process.
No Image
Pages : 1