Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 68.158 68.158 36.121 96.121 188.445 53% 24%
May - 2021
02 units Work in progress.
No Image
  1. Package I (KM 22 to 30) 09 KM
  2. Package II (KM 31 to 39) 09 KM
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 68.158 68.158 36.121 96.121 188.445 53% 24%
April - 2021
02 units Work in progress.
No Image
  1. Package I (KM 22 to 30) 09 KM
  2. Package II (KM 31 to 39) 09 KM
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 150 68.158 18.366 78.366 188.445 53% 20%
December - 2020
Work in progress.
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 150 68.158 18.366 78.366 188.445 53% 20%
December - 2020
Work in progress.
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 150 45 18.366 78.366 188.445 53% 20%
October - 2020
Work in progress.
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 150 45 0 60 188.445 53% 15%
September - 2020
Work in progress.
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 150 0 0 60 188.445 53% 15%
August - 2020
Work in progress.
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 0 150 0 0 0 0 0 -
July - 2020
No Image
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 68.158 68.158 36.121 96.121 188.445 53% 24%
March - 2021
02 units Work in progress.
No Image
  1. Package I (KM 22 to 30) 09 KM
  2. Package II (KM 31 to 39) 09 KM
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 68.158 68.158 36.121 96.121 188.445 53% 24%
February - 2021
02 units Work in progress.
No Image
  1. Package I (KM 22 to 30) 09 KM
  2. Package II (KM 31 to 39) 09 KM
1934
(OG)
195271-Construction of Road from Khoi Bahara via village Umerzai Astandar to Parwara Road NA-50, (18-KMs) in Sub Division Darazinda (TR) (AIP)
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 398.445 60 150 68.158 68.158 36.121 96.121 188.445 53% 24%
January - 2021
Work in progress.
No Image
Pages : 1