Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 51.357 | 0 | 0 | 640.95 | 24% |
- December - 2020 |
joint survey in progress with NESPAk for last 2 months |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 51.357 | 0 | 0 | 640.95 | 24% |
- December - 2020 |
joint survey in progress with NESPAk for last 2 months |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 60 | 0 | 0 | 640.95 | 24% |
- October - 2020 |
Work in progress. |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 0 | 0 | 0 | 640.95 | 24% |
- September - 2020 |
layout under process. |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 0 | 0 | 0 | 640.95 | 24% |
- August - 2020 |
Procurement under process. |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 200 | 51.357 | 0 | 0 | 640.95 | 24% |
- January - 2021 |
joint survey in progress with NESPAk for last 2 months |
No Image |
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 167.407 | 167.407 | 8.32 | 8.32 | 640.95 | 24% |
1% March - 2021 |
03 Units
1 Joint survey with NESPAK
2 work in progress
3 work in progress |
No Image |
| |||||||||||||||||||
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 167.407 | 167.407 | 8.32 | 8.32 | 640.95 | 24% |
1% February - 2021 |
03 Units
1 Joint survey with NESPAK
2 work in progress
3 work in progress |
No Image |
| |||||||||||||||||||
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 67.407 | 67.407 | 61.107 | 61.107 | 640.95 | 24% |
7% May - 2021 |
03 Units
1 Joint survey with NESPAK
2 work in progress
3 work in progress |
No Image |
| |||||||||||||||||||
1933 (OG) |
195273-Improvement & Widening of Main Jandola Gabbar Road (42-KMs) (TR) (AIP) |
Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 840.95 | 0 | 200 | 67.407 | 67.407 | 61.107 | 61.107 | 640.95 | 24% |
7% April - 2021 |
03 Units
1 Joint survey with NESPAK
2 work in progress
3 work in progress |
No Image |
| |||||||||||||||||||