Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
30-11--1 30-11--1 - 30-11--1 - 46.249 0 15 0 0 0 0 31.249 32% -
July - 2020
Work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 15 7.352 0 25 6.249 86% 54%
December - 2020
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 15 7.352 0 25 6.249 86% 54%
December - 2020
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 15 5 0 25 6.249 86% 54%
October - 2020
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 15 5 0 25 6.249 86% 54%
September - 2020
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 15 0 0 25 6.249 86% 54%
August - 2020
Earth work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 7.352 7.352 0 25 6.249 86% 54%
May - 2021
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 7.352 7.352 0 25 6.249 86% 54%
April - 2021
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 7.352 7.352 0 25 6.249 86% 54%
March - 2021
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 7.352 7.352 0 25 6.249 86% 54%
February - 2021
Earth work & S/work in progress.
No Image
1926
(OG)
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 46.249 25 15 7.352 7.352 0 25 6.249 86% 54%
January - 2021
Earth work & S/work in progress.
No Image
Pages : 1