Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
30-11--1 30-11--1 - 30-11--1 - 106.06 0 30 0 0 0 0 76.06 28% -
July - 2020
Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 30 11.004 3.842 16.842 63.06 41% 16%
December - 2020
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 30 11.004 3.842 16.842 63.06 41% 16%
December - 2020
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 30 7 0 13 63.06 41% 12%
October - 2020
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 30 7 0 13 63.06 41% 12%
September - 2020
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 30 0 0 13 63.06 41% 12%
August - 2020
Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 18.704 18.704 18.579 31.579 63.06 41% 30%
May - 2021
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 18.704 18.704 18.579 31.579 63.06 41% 30%
April - 2021
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 18.704 18.704 3.824 16.824 63.06 41% 16%
March - 2021
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 18.704 18.704 5.759 18.759 63.06 41% 18%
February - 2021
Earth Work in progress.
No Image
1925
(OG)
195259-Construction and Black Topping of Naranj to Ghargo Sar Road (4-KMs) Bajaur (FMR) (AIP)
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 106.06 13 30 18.704 18.704 3.842 16.842 63.06 41% 16%
January - 2021
Earth Work in progress.
No Image