Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 0 0 0 0 157.26 24% -
July - 2020
Procurement under process.
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 50 17.839 0 0 157.26 24% -
December - 2020
Work order issued. Survey Strated. Court stay vacated
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 50 17.839 0 0 157.26 24% -
December - 2020
Work order issued. Survey Strated. Court stay vacated
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 50 10 0 0 157.26 24% -
October - 2020
Procurement under process.
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 50 10 0 0 157.26 24% -
September - 2020
Procurement under process.
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 50 10 0 0 157.26 24% -
August - 2020
Procurement under process.
No Image
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 504.838 0 50 7.839 7.839 7.839 7.839 454.838 10% 2%
May - 2021
02 Units 1. Work recently started 2. Tender floated
No Image
Rehab: of Main Jamrud road Warsak Dam 25 KM
Sub Head:
i. Rehab: of Main Jamrud road warsak Road to Shahgai Thana 13 KM
ii. Rehab: of road form Shahgai Thana to Warsak Dam 12 KM
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 504.838 0 50 7.839 7.839 7.839 7.839 454.838 10% 2%
April - 2021
02 Units 1. Work recently started 2. Tender floated
No Image
Rehab: of Main Jamrud road Warsak Dam 25 KM
Sub Head:
i. Rehab: of Main Jamrud road warsak Road to Shahgai Thana 13 KM
ii. Rehab: of road form Shahgai Thana to Warsak Dam 12 KM
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 504.838 0 50 17.839 17.839 0 0 454.838 10% -
March - 2021
02 Units 1. Work recently started 2. Tender floated
No Image
Rehab: of Main Jamrud road Warsak Dam 25 KM
Sub Head:
i. Rehab: of Main Jamrud road warsak Road to Shahgai Thana 13 KM
ii. Rehab: of road form Shahgai Thana to Warsak Dam 12 KM
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 504.838 0 50 17.839 17.839 0 0 454.838 10% -
February - 2021
02 Units 1. Work recently started 2. Tender floated
No Image
Rehab: of Main Jamrud road Warsak Dam 25 KM
Sub Head:
i. Rehab: of Main Jamrud road warsak Road to Shahgai Thana 13 KM
ii. Rehab: of road form Shahgai Thana to Warsak Dam 12 KM
1917
(OG)
195282-Rehabiliation of Main Jamrud Warsak Road to Shahgai Thana (13 Kms) Khyber (ER) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 207.26 0 50 17.839 17.839 0 0 157.26 24% -
January - 2021
Work order issued. Survey Strated. Court stay vacated
No Image
Pages : 1