Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 0 | 0 | 0 | 75 | 59 | 71% |
37% July - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 70 | 30.975 | 7.83 | 82.83 | 59 | 71% |
41% December - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 70 | 30.975 | 7.83 | 82.83 | 59 | 71% |
41% December - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 70 | 20 | 0 | 75 | 59 | 71% |
37% October - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 70 | 20 | 0 | 75 | 59 | 71% |
37% September - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 70 | 20 | 0 | 75 | 59 | 71% |
37% August - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 30.975 | 30.975 | 30.975 | 105.975 | 59 | 71% |
52% May - 2021 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 30.975 | 30.975 | 30.975 | 105.975 | 59 | 71% |
52% April - 2021 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 30.975 | 30.975 | 30.975 | 105.975 | 59 | 71% |
52% March - 2021 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 30.975 | 30.975 | 30.975 | 105.975 | 59 | 71% |
52% February - 2021 |
Earth work, Road work and Structure work in progress. |
No Image |
1912 (OG) |
195245-Construction & B/Topping road from Shaheed Manza to Ghalmi Aka Khel Mirghat Khel (10-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204 | 75 | 70 | 30.975 | 30.975 | 7.83 | 82.83 | 59 | 71% |
41% January - 2021 |
Earth work, Road work and Structure work in progress. |
No Image |
Pages : 1 |