Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 0 | 150 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 96.518 | 96.518 | 84.09 | 239.09 | 179.305 | 63% |
49% May - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-7
Package 2 KM 8-15
| |||||||||||||||||||
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 45 | 45 | 32.183 | 187.183 | 179.305 | 63% |
39% December - 2020 |
Work in progress. |
No Image |
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 45 | 45 | 32.183 | 187.183 | 179.305 | 63% |
39% December - 2020 |
Work in progress. |
No Image |
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 150 | 45 | 0 | 155 | 179.305 | 63% |
32% October - 2020 |
Work in progress. |
No Image |
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 150 | 45 | 0 | 155 | 179.305 | 63% |
32% September - 2020 |
Work in progress. |
No Image |
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 150 | 45 | 0 | 155 | 179.305 | 63% |
32% August - 2020 |
Work in progress. |
No Image |
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 96.518 | 96.518 | 58.317 | 213.317 | 179.305 | 63% |
44% April - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-7
Package 2 KM 8-15
| |||||||||||||||||||
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 73 | 73 | 41 | 196 | 179.305 | 63% |
40% March - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-7
Package 2 KM 8-15
| |||||||||||||||||||
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 73 | 73 | 41 | 196 | 179.305 | 63% |
40% February - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-7
Package 2 KM 8-15
| |||||||||||||||||||
1910 (OG) |
195302-Widening & Improvement of Parachinar Borki Road via Karakhela (15 KMs) (BC) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 484.305 | 155 | 150 | 73 | 73 | 25.336 | 180.336 | 179.305 | 63% |
37% January - 2021 |
Work in progress. |
No Image |
Pages : 1 |